6.2.2
Main bearing - install the cover
Periodicity
Description
Working hours
90 000
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
2.0 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Basic
AR
Support equipment
Description
Part No.
CSN
QTY
Spur-geared chain block,
2500 kg
94017-028
1
Thrust device
94110
1
Lug
94116C
1
Shackle 6500 kg
94019K
1
Shackle 2000 kg
94019G
1
HP oil pump
94931
1
Supplies
Description
QTY
None
Spare Parts
Description
Part No.
CSN
QTY
Main bearing cover
1
SAFETY PRECAUTIONS
•
None
PRELIMINARY OPERATIONS
•
The bearing shell must be installed, refer to section
6.2.2 Main bearing - install the cover
•
The work area and all tools and equipment must be clean and in good condition.
X72DF
AA00-1132-00AAA-720A-A
Maintenance Manual
Main bearing - install the cover
Winterthur Gas & Diesel Ltd.
- 110 -
Issue 002 2020-10
Summary of Contents for X62DF
Page 881: ...Approved Tightening Instructions Rev I Page 1 14...
Page 882: ...Approved Tightening Instructions Rev I Page 2 14...
Page 883: ...Approved Tightening Instructions Rev I Page 3 14...
Page 884: ...Approved Tightening Instructions Rev I Page 4 14...
Page 885: ...Approved Tightening Instructions Rev I Page 5 14...
Page 886: ...Approved Tightening Instructions Rev I Page 6 14...
Page 887: ...Approved Tightening Instructions Rev I Page 7 14...
Page 888: ...Approved Tightening Instructions Rev I Page 8 14...
Page 889: ...Approved Tightening Instructions Rev I Page 9 14...
Page 890: ...Approved Tightening Instructions Rev I Page 10 14...
Page 891: ...Approved Tightening Instructions Rev I Page 11 14...
Page 892: ...Approved Tightening Instructions Rev I Page 12 14...
Page 893: ...Approved Tightening Instructions Rev I Page 13 14...
Page 894: ...Approved Tightening Instructions Rev I Page 14 14...