Winco PSS30 Installation And Operation Manual Download Page 8

Page 6

0210-00

60706-195

Connect the fuel supply to the inlet of the fuel solenoid (see table
for recommended line size).  The pressure at the secondary
demand regulator must be four to six ounces psi (per square
inch) or 7 to 11 inches W.C. (Water column)  for vapor withdrawal
units.  On units equipped with liquid withdrawal fuel systems full
tank pressure is plumbed to the fuellock strainer mounted on the
generator rails.  The fuel converter mounted on the unit will
handle both vaporization of the fuel and pressure reduction.

INSTALLING THE FUEL LINE

** NOTICE **

The engine generator sets are properly adjusted before they
leave the factory for a specific fuel, either NG (natural gas), LP
(liquid  propane vapor) or LPG (liquid withdrawal propane).  This
fuel type is noted in your model number.  If it becomes necessary
to change the fuel type in the field see information on page 12.

Line Size (vapor system)

Unit location will determine the size of fuel line that is required to
supply the engine with a constant fuel pressure.  Refer to the
tables below for fuel line size, fuel consumption and recom-
mended tank size.  For distances of 25 feet and over, a two
regulator fuel system is recommended.  This is accomplished by
installing a primary regulator at the tank which will reduce the
tank pressure down to 10 to 15 lbs.  A secondary regulator is
installed to further reduce the fuel pressure to the required six (6)
oz operating pressure.  This secondary regulator must be at least
10 feet from the engine generator set.  Any closer installation will
require a larger line be installed to provide a fuel reservoir.   If this
is not done, the demand regulator on the unit and the pressure
regulator in the fuel line will interfere with each other.  When this
two (2) stage regulator system is used, a fuel line size of 3/4 to 1
inch is generally adequate for distances up to 300 feet from the
primary to the secondary regulator.  (Consult your local fuel
supplier for your exact requirements). The appropriate line size
from the table below is then installed from the secondary regula-
tor to the generator set.

****************

*****  WARNING  *****

****************

PERSONAL DANGER - Do not use galvanized pipe in fuel line
runs.  The galvanized coating can become eroded and flake off,
causing possible obstructions in the regulator or fuel valve.  The
results could range from inoperative engine start to hazardous
fuel leaks.

Size of pipe normally required for generators operating on NG/LP:

       up to 25 feet*              over 25 feet*

PSS30

   1" pipe                   not recommended

PSS40

   1" pipe             use a two regulator system

* Allow an additional 3 feet for each standard elbow.

 Do not use ‘street ells’ (restrictive).

****  CAUTION  ****

EQUIPMENT DAMAGE - Be careful when sealing gas line joints.
Excessive sealing compound can be drawn into the solenoid,
regulator or carburetor causing an engine malfunction.

FUEL PRESSURE (vapor system)

Correct fuel pressure cannot be stressed enough.  The most
common cause for inoperative systems is an inadequate or
incorrect fuel pressure.  Performance of the engine is in direct
relation to the correctness of the fuel system.  Shown below is a
block diagram of a typical L.P. or N.G. Installation.

 Supply

   Primary

 Secondary

Generator

  Tank

   Regulator

 Regulator

   Set

        1                  2

3

    4

TWO (2) REGULATOR FUEL SYSTEM

   Supply

       Primary

Generator

    Tank

Regulator

     Set

1

2

4

SINGLE REGULATOR FUEL SYSTEM

Reference numbers 1 through 3 in the block diagrams above are
fuel lines supplied by customer.

Reference number 4 is the engine generator set.

Below is a table of the fuel pressure readings at each reference in
the system.

Fuel Pressure Table

Single Regulator (L.P. Vapor only)

1

2

3

UNIT OFF

TANK PSI

7-11 in

7-11 in

4-6 oz

4-6 oz

STARTING

TANK PSI

7-11 in

7-11 in

4-6 oz

4-6 oz

NO LOAD

TANK PSI

7-11 in

7-11 in

4-6 oz

 4-6 oz

FULL LOAD

TANK PSI

7-11 in

7-11 in

4-6 oz

4-6 oz

Two (2) Regulator System (L.P. Vapor only)

1

2

3

4

UNIT OFF

TANK PSI

10-15 lbs

7-11 in

7-11 in

4-6 oz

4-6oz

STARTING

TANK PSI

10-15 lbs

7-11 in

7-11 in

4-6 oz

4-6 oz

NO LOAD

TANK PSI

10-15 lbs

7-11 in

7-11 in

4-6 oz

4-6 oz

FULL LOAD TANK PSI

10-15 lbs

7-11 in

7-11 in

4-6 oz

4-6 oz

Natural Gas

1

2

4

UNIT OFF

LINE PSI

7-11 in

7-11 in

4-6 oz

4-6 oz

STARTING

LINE PSI

7-11 in

7-11 in

4-6 oz

4-6 oz

NO LOAD

LINE PSI

7-11 in

 7-11 in

4-6 oz

4-6 oz

FULL LOAD

LINE PSI

7-11 in.

7-11 in

4-6 oz

4-6 oz

Summary of Contents for PSS30

Page 1: ...PACKAGE STANDBY SYSTEMS INSTALLATION AND OPERATIONS MANUAL PSS30 B PSS40 E...

Page 2: ...ned SAVE THESE INSTRUCTIONS This manual contains important instructions that should be followed during installation and maintenance of the generator and batteries Read and understand all instructions...

Page 3: ...electrician or contractor The installation must comply with all national state and local codes g Always make sure unit is disabled before placing your hands anywhere near the fan belts alternator or...

Page 4: ...er liquid cooled engine equipped to run on L P N G fuel The engine operates at 1800 rpm and frequency regulation is maintained by the electronic governor within 5 cycles variation from no load to rate...

Page 5: ...emperature monitoring over crank protection ECU specific protection elements and diagnostic reporting Metered engine parameters include oil pressure coolant A Liquid Crystal Display The backlit 64 by...

Page 6: ...setting or resetting the system clock 1 Press K right key for initial set or K left to back up up down to choose menu item and time date element to be changed 2 Press L Edit to access change mode to e...

Page 7: ...engine s requirements and assist in making you aware of the decisions you must make In no case should the instructions or information provided be interpreted to conflict with any local state or natio...

Page 8: ...nstalled from the secondary regula tor to the generator set WARNING PERSONAL DANGER Do not use galvanized pipe in fuel line runs The galvanized coating can become eroded and flake off causing possible...

Page 9: ...performed or supervised only by personnel knowledgeable of batteries and the required precautions Keep unauthorized personnel away from batteries When installing or replacing batteries use the proper...

Page 10: ...e to do so can cause damage to the engine control module in the generator set All connections must be clean and tight Check the electrolyte fluid in the battery periodically to be sure it is above the...

Page 11: ...t Terminal Block This terminal block is provide for the 120 volt 15 amp feed from customers distrubution panel for the block heater and the trickle charger WARNING A main line circuit breaker has been...

Page 12: ...will not start and run without either the jumper installed or a remote N C switch installed G Fuel Select Toggle Switch This SWITCH allows you to change the engine from one fuel to the other See Chang...

Page 13: ...generator terminals in the Automatic Transfer Switch The voltage between the G1 and the G3 terminals should be the same as it was on the generator front panel The voltage should also be checked betwe...

Page 14: ...3 Governor is defective 4 AC short in generator components ATS PANEL WILL NOT TRANSFER TO EMERGENCY SUPPLY GENERATOR 1 No AC generator output from generator 2 Defective transfer switch controller 3 In...

Page 15: ...60706 195 Page 13 0210 00 VOLTAGE REGULATOR WIRING THREE PHASE AND SINGLE PHASE...

Page 16: ...Page 14 0210 00 60706 195 THREE PHASE AC WIRING HIGH AND LOW WYE THREE PHASE LOW WYE 120 208 VOLTS THREE PHASE HIGH WYE 277 480 VOLTS...

Page 17: ...60706 195 Page 15 0210 00 THREE PHASE AC WIRING DELTA SINGLE PHASE AC WIRING SINGLE PHASE 120 240 VOLTS THREE PHASE DELTA 120 240 VOLTS...

Page 18: ...Page 16 0210 00 60706 195 DC SCHEMATIC...

Page 19: ...0706 195 Page 17 0210 00 PSS30 OUTLINE DRAWING AND WIRING ENTRANCE PSS40 OUTLINE DRAWING AND WIRING ENTRANCE DIMENSIONS ARE SUBJECT TO CHANGE ALWAYS OBTAIN A CERTIFIED DRAWING FOR CONSTRUCTION PURPOSE...

Page 20: ...e are limited to 12 months or 1000 hours which ever accurs first from date of purchase In no event is WINCO liable for incidental or consequential damages Note Some states do not allow limitation on t...

Reviews: