INSULATION BLANKET INSTALLATION, CONTINUED
1. Spray the top of the evaporator unit with spray adhesive. (See spray adhesive directions for proper tack time
before proceeding to step 8.)
2. Set piece (B) in place by pressing firmly on all surfaces of the insulation that come in contact with the top of the
evaporator unit (see illustration).
3. Using a utility knife, cut holes in the insulation for line set, wiring, and drain line if needed.
4. Once insulation is installed, apply foil tape to all seams, covering them completely.
5. Inspect insulation for damage/defects. If damaged, repair with foil tape.
6. Apply cork tape or equivalent to areas where the line set, wiring, and drain line enter the unit.
If needed, trim excess insulation around all edges.