6.14. Support the Plenum Peak Ring
Position the plenum peak ring as follows:
1. Using
and
, support the plenum peak ring in the center of the bin at the correct height.
a. Use a center jack or wood scaffold.
b. Make certain the peak ring is as level as possible.
Figure 19.
Setting the Height of the Plenum Peak Ring
TOP SIDEWALL TIER
(Installed a
ft
er Plenum
construc
ti
on is complete)
PLENUM
PEAK RING
24’ – 006199
27’ – 006172
30’ – 006153
36’ – 004825
Hp
CENTER JACK
SECOND AND THIRD
SIDEWALL TIERS
Table 9.
Plenum Peak Height
Nominal Bin
Diameter
Scribe Radius
Bottom of Plenum Peak Ring
Height "Hp" with 1 tier of
wall sheets
Bottom of Plenum Peak Ring
Height "Hp" with 2 tiers of
wall sheets
(ft)
(ft in)
(m)
(ft in)
(m)
(ft in)
(m)
24
11'10-1/2"
3.619
8'2-5/8"
2.505
11'10-5/8"
3.623
27
13'4-3/8"
4.074
9'1-3/4"
2.788
12'9-3/4"
3.906
30
14'10-5/16"
4.529
10'1"
3.074
13'9"
4.191
36
17'10-1/8"
5.438
11'11-1/2"
3.645
15'7-1/2"
4.763
EASYDRY® WIDE-CORR CENTURION® GRAIN BIN – GRAIN BIN DRYER