3.
Once the wall bracket support has been removed, start stacking the second module in correspondence with the
first module laid on the ground.
The battery weighs more than 52kg and must be installed with the help of a mechanical lift, and / or with at
least two people equipped with suitable suction cups for mechanical lifting or lifting straps
4.
Continue the installation with the desired modules following the sequence described in the previous points.
5.
Connect the power cables as indicated, making sure that the batteries are
OFF
(check the button LED on
the bottom) and always measure the terminals with a multimeter.
1-First module on the ground platform
2-Lift the second module and place it on the
first module