Operation & Maintenance Manual
7 |
P a g e
4.2 Extent of Supply
See the delivery note for full details. The standard unit comes with the following:
A GRP tank, incorporating the two sections
A blower kiosk with blower and control panel fitted.
Items supplied loose will be found either inside the filter section or on a separate pallet.
4.3 Electrical Equipment
All electrical equipment, including blowers, must be stored in clean dry conditions until required for use.
If the electrical equipment is fitted into the kiosk, some form of anti-condensation heater will be required
if the unit is not to run immediately. (Data Sheets for electrical components can be found in appendix 3).
4.4 Bolts and Bolt Strips
Due to the settling of the joints during transportation of the unit, the bolts may become loose and need
tightening. It is important that the bolt strips are not overtightened as this can cause leaks.
Tighten all bolts in the metal strips to 50Nm to ensure all the foam is compressed then tighten up to a
final value of 60Nm. Silo Bolts (with no metal strips) around the top of the unit should only be tightened
to 30Nm.
Closed Cell
Foam Strip
50 then 60 NM
(35 then 44 lb.ft)
Pinched Foam Strip
Can Cause Leaks
CAUTION Do Not Over Tighten