Setting the Sustaining Control

STEP 7

Slowly open downstream isolation valve to establish flow through 
the system.

STEP 8

Setting the Sustaining Control requires lowering the upstream 
pressure to the desired minimum sustained pressure.

STEP 9

Leave the downstream isolation valve full open and close the 
upstream isolation valve until the inlet pressure drops to the 
desired setting.

STEP 10

Adjust the Sustaining Control screw IN, clockwise, until the inlet 
pressure begins to increase (See Figure 4A), or OUT, counter-
clockwise (See Figure 4B), to decrease, stopping at the desired 
pressure.

STEP 11

Allow pressure to stabilize.

STEP 12

Fine-tune the sustaining setting as required as detailed in STEP 
10.

STEP 13

Open upstream isolation valve to return to normal operation.

4          IOM-ACV-127-8_6127-8 2115 

EDP# 1917065 

© 2021 Watts

IOM-ACV-127-8_6127-8 2115 

EDP# 1917065 

© 2021 Watts         5

5A

5B

Figure 5 

PV20C — Pressure Sustaining Control

Clockwise to increase inlet 

pressure

Counterclockwise to decrease 

inlet pressure

Summary of Contents for LFM127-8

Page 1: ...on 2 Setting the Altitude Controls 3 Maintenance Schedule 6 Trouble Shooting Guide 6 Valve Disassembly Instructions 8 ACV Schematic 11 Local building or plumbing codes may require modifica tions to the information provided You are required to consult the local building and plumbing codes prior to installation If the information provided here is not consistent with local building or plumbing codes ...

Page 2: ...lowing instructions on Technical Bulletin Start up of an automatic control valve requires that proper procedures be followed Time must be allowed for the valve to react to adjustments and the system to stabilize The objective is to bring the valve into service in a controlled manner to protect the system from damaging over pressure installed sensing line and directs pressure into and out of the co...

Page 3: ...wly open the valve See Figure 1 STEP 3 Pressure the line by opening the upstream isolation valve slowly Air is vented through the air bleed valve Tighten the fitting when liquid begins to vent See Figure 1 Repeat the process until no air is trapped in the system Globe Angle Size in 11 4 11 2 2 21 2 3 4 6 8 10 12 14 16 20 24 A in 16 16 20 22 22 24 32 34 38 44 48 52 56 56 B in 10 10 12 14 14 16 24 2...

Page 4: ...r of the main valve If recovery of pressure is slow upon increased downstream demand turn the adjustment screw OUT counterclockwise increasing the rate of opening See Figure 2B If recovery of downstream pressure is too quick as indicated in a rapid increase in pressure possibly higher than the desired set point turn the adjustment screw IN clockwise decreasing the rate of opening See Figure 2A STE...

Page 5: ...red setting STEP 10 Adjust the Sustaining Control screw IN clockwise until the inlet pressure begins to increase See Figure 4A or OUT counter clockwise See Figure 4B to decrease stopping at the desired pressure STEP 11 Allow pressure to stabilize STEP 12 Fine tune the sustaining setting as required as detailed in STEP 10 STEP 13 Open upstream isolation valve to return to normal operation IOM ACV 1...

Page 6: ...e specification sheets for approximate cover capacity A continuous flow of water from the open port indicates a damaged diaphragm or loose disc diaphragm assembly Disassemble valve and replace diaphragm or tighten disc diaphragm assembly Test 2 Seat Seal Test 1 Close downstream isolation valve and install pressure gauges on an open inlet and outlet port of main valve 2 Open upstream isolation valv...

Page 7: ... 2 1 2 turns open from full closed position Can be adjusted in field Main Valve will not close Closed isolation valves in pilot system Check isolation valves ensure open Diaphragm is damaged Conduct diaphragm seal test repair and replace if necessary Main valve stem assembly corroded damaged Inspect stem assembly clean replace if necessary Blockage in main valve Perform freedom of movement test if...

Page 8: ... Remove cover nuts and washers 3 Remove the cover If cover is not free to be removed loosen it by tapping upward along its outside edge with a dull cold chisel pic tured above a Large valves may require the installation of lifting eye bolts in order to facilitate cover removal installation ports are provided on the cover for this purpose 4 Remove the Disc and Diaphragm Assembly from the valve body...

Page 9: ... brush or by using a Mineral Dissolving Solution Inspect parts for wear and replace if necessary 7 Inspect valve seat If seat is not damaged removal is not necessary Valve seats 6 and smaller are threaded into the body of the valve and require a seat removal tool Figure 6 Table 1 details the tool dimensions for seat removal Valve seats 8 and larger are held in the valve body with stainless steel c...

Page 10: ... Nuts in a crossing pattern to ensure even distribution Test the Disc and Diaphragm Assembly for smooth travel by following the Freedom of Movement Test procedure in previous section 11 Test the integrity of the Seat Seal by following the Seat Seal Test procedure in previous section 12 Return valve to service by following instructions on the Technical Bulletin matching the valve function Size in 1...

Page 11: ...l 9 Stem Washer ASTM A276 304 Stainless Steel 10 Diaphragm Washer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 11 Diaphragm Buna N Nitrile 12 Disc Retainer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 13 Seat Disc Buna N Nitrile 14 Spacer Washer x5 NY300 Fiber 15 Disc Guide ASTM A743 CF8M 316 Stainless Steel 16 Shaft ASTM A276 304 Stainless Steel 17 Seat Ring ASTM A743 CF8M 316 Stainless Steel 17A...

Page 12: ...ot be responsible for any incidental special or consequential damages including without limitation lost profits or the cost of repairing or replacing other property which is damaged if this product does not work properly other costs resulting from labor charges delays vandalism negligence fouling caused by foreign material damage from adverse water conditions chemical or any other circumstances ov...

Reviews: