9.2 Replacing the Reagent Pump  
(Kit #28167S)

To replace the reagent pump on the CSM instrument:
1.  Loosen the 2 screws that hold the reagent pump bracket to the 

back panel.

2.  Lift the bracket assembly off of the screws.
3.  Unscrew the colored fittings from the reagent pump.
4.  Unplug the wire connection from the reagent pump.
5.  Unscrew the 2 screws holding the reagent pump to the mounting 

block.

6.  Install new reagent pump to the mounting block using the 2 screws 

removed in Step 5.

7.  Plug wire connections into new reagent pump.
8.  Screw in the colored fittings to new reagent pump.
9.  Screw the reagent pump bracket to the back panel using the 2 

screws that were loosened in Step 1.

Loosen screws.

Unscrew colored fittings.

9.3 Replacing the Peristaltic Pump  
(Kit #28141S)

To replace the peristaltic pump on the CSM instrument:
1.  Push tabs in on sides and pull up to 

remove the pump head from the base.

2.  Remove existing clamps and detach 

hoses. Take care to keep hose ends in 

good condition and note which hose 

is connected to the IN and which is 

connected to the OUT; these will need 

to be reattached to the new pump head 

in the same order.

3.  Based on the arrows between the pump 

head fittings, reattach the IN hose to the 

IN pump head fitting and the OUT hose to 

the OUT pump head fitting. Secure using 

the new clamps. 

4.  Align the cutout of the pressure rotor with the cutout 

in the base.  

5.  Lower the new pump head down to securely reattach it to the base.

9.4 Replacing the Pressure Regulator 
Assembly (Kit #28190S)

To replace the pressure regulator assembly on the CSM instrument:
1.  Turn off water to the CSM instrument.
2.  Loosen the screws on the bracket connecting the pressure regulator 

to the back panel.

3.  Lift bracket and attached components from back panel.
4.  Loosen the water inlet tube (orange) from the pressure regulator.

5.  Remove the panel nut that holds the regulator in place.
6.  Lower the regulator down through the bracket.
7.  Remove fittings (x2) from inlet and outlet of regulator. Be sure to 

note “IN and “OUT” positions of the regulator.

8. Clean off the old fittings and apply new Tellon tape to the 

threads of the fittings.

9.  Reinstall the fittings into the new regulator in the same orientation 

as the original. Be sure the “IN” and “OUT” positions are orientated 

the same as the old regulator. “IN” and “OUT” are labeled on the 

pressure regulator.

Panel 

Nut

Water Inlet 

Tube

Remove Inlet 

Fitting and 

Clean

Remove 

Outlet Fitting 

and Clean

Inlet Label 

(White Fitting, 

Orange 

Connector, 

Clear Tubing)

Outlet Label 

(Black Fitting, 

Black Tubing)

1

3

5

4

7

7

9

9

Take note of the orientation of the check valves and tubing. The 

placement of these items depends on the orientation of the pump 

being replaced. To change the orientation of the new pump, loosen 

thumb screw from the pump, remove check valves and tubing and 

route to the opposite side of pump. Tighten thumb screw. The check 

valve always needs to be towards the front of the pump when looking 

into the enclosure from the front.

NOTICE

Unplug wire connection

Unscrew 2 screws

Thumb Screw

Note routing of tubing based on 

orientation of pump

4

5

Summary of Contents for HF Scientific CSM

Page 1: ...ilver Monitor IS HF CSM 100184 WARNING Read this Manual BEFORE using this equipment Failure to read and follow all safety and use information can result in death serious personal injury property damage or damage to the equipment Keep this Manual for future reference Rev 1 ...

Page 2: ...ing the Units of Measurement 7 5 3 Setting the Date Time 7 5 4 Adjusting the Brightness 7 5 5 Setting the Time Schedule 7 5 6 Setting the Reading Mode 8 5 7 Adjusting the Line Flush Duration 8 5 8 Security Setting 8 5 9 Firmware Update 9 5 10 Copying FRAM data to SD Card 9 5 11 Factory Reset 10 5 12 About Device 10 6 0 System Start Up 10 6 1 Prepare Reagents 10 6 2 Priming the CSM 10 6 3 Taking Re...

Page 3: ...nt This pictorial alerts you to the need to read the manual This pictorial alerts you to electricity electrocution and shock hazards 1 0 Understanding Safety Information This manual contains safety and use instructions that must be followed during the installation commissioning operation care and maintenance and service of the CSM All responsible personnel must read this manual prior to working wi...

Page 4: ...o 23 hours 59 minutes Path Length 10mm Display 3 5 Color graphic touch screen Analog Output Powered 4 20mA 1000 Ω drive isolated Maximum Water Pressure 124 kPa 18 psi see Plumbing Connections section Flow Rate 185 ml min to 225 ml min 044 to 059 Gal min Operating Temperature 1 C 50 C 34 F 122 F Max Sample Water Intake and Drainage Flow 225 ml minute Wetted Materials PBT Polypropylene 316 Stainless...

Page 5: ...be removed for easier connections Please ensure this terminal set is properly tightened using the two side screws 3 2 Plumbing Connections All plumbing connections are made with user supplied OD tubing using the push to connect fittings attached to the CSM All water tubing used to connect to the CSM is supplied by the installer Sample water should be particulate free The sample water supply does n...

Page 6: ...electrical panel and tighten Securing the Electrical Enclosure Once all electrical connections are made the electrical panel must be secured by closing the compartment and tightening the captive Phillips screw 4 0 Commissioning and Start Up 1 Once all water and electrical connections have been made turn on power to the CSM 2 The CSM will run through a startup process that takes less than 10 second...

Page 7: ...ve 4 Once the date and time have been saved press the button to return to the home screen or press Cancel to return to the previous menu 5 4 Adjusting the Brightness The screen brightness can be adjusted to provide easier readability of the display in low light or no light conditions There are 10 brightness levels available To adjust the screen brightness 1 Press Brightness on the Configuration Me...

Page 8: ... suggested line flush duration is 1 second for every foot of sample line tubing assuming inlet pressure of 4 60psi To adjust the line flush duration 1 Press Line Flush Setting on the Configuration Menu screen 2 Using the up and down arrows set the desired duration for the line flush in seconds 3 Once the desired Line Flush Duration has been saved press the button to return to the home screen or pr...

Page 9: ...ate is complete a restart of the instrument is required Do not remove the SD card or turn power off while the software update is in progress Doing so can cause an unrecoverable failure NOTICE 5 10 Copying FRAM data to SD Card The following information from the CSM can be transferred to an SD card in CSV file format Readings Error and warning logs with date and time stamps All user settings Calibra...

Page 10: ...he prime sub menu 3 Press the desired priming option If this is the first time starting up the instrument start with Prime Water and repeat this step for all priming options in this menu Reagent Bags Hanging on Brackets P N 110097 Assembled in the USA Reagent Kit Copper Indicator 16260 Airport Park Drive Suite 140 Fort Myers FL 33913 L 74125 Rev E 11 2020 WARNING Harmful if swallowed Causes skin i...

Page 11: ...per Silver 500 ml Solution C in Cal Procedure DI Water 500 ml Solution D in the Cal Procedure To recalibrate the CSM follow the prompts on the screen 1 From the screen press Service to enter the Service Menu 2 Press CALIBRATE to begin the Calibration sequence Ensure you have the calibration kit ready then press NEXT 3 Turn off the water supply Press Next There is a removable light shield attached ...

Page 12: ...placement Kit To order any accessory or replacement parts please contact the HF scientific Customer Service Department HF scientific 16260 Airport Park Drive Suite 140 Fort Myers FL 33913 Phone 239 337 2116 Toll Free 888 203 7248 Fax 239 454 0694 Email hf info wattswater com Website www hfscientific com 4 Disconnect the upper inlet tubing hose from the peristaltic pump and attach a single piece of...

Page 13: ...gent tubing skip to step 16 12 Insert short piece of new tubing into outlet fitting on solenoid valve Insert other end into inlet fitting into optical injector 13 Secure solenoid valve to bracket with 2 screws removed in step 6 14 Insert end of new tubing into inlet of the solenoid valve 15 Reuse Velcro strap to secure the reagent tubing check valves to the top of the pump bracket 16 Guide tubing ...

Page 14: ...the base 9 4 Replacing the Pressure Regulator Assembly Kit 28190S To replace the pressure regulator assembly on the CSM instrument 1 Turn off water to the CSM instrument 2 Loosen the screws on the bracket connecting the pressure regulator to the back panel 3 Lift bracket and attached components from back panel 4 Loosen the water inlet tube orange from the pressure regulator 5 Remove the panel nut ...

Page 15: ...pump to the optical board and then remove air pump 11 Insert new air pump Be sure the arrow on the new air pump is facing the correct direction 12 Install 2 screws from underneath air pump bracket 13 Attach air pump to optical board using the included zip tie 14 Screw in black fitting into air pump outlet 15 Reconnect the black and pink air pump wiring connection located in the electrical panel 16...

Page 16: ...IMPLIED WARRANTIES OR MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE The remedy described in the first paragraph of this warranty shall constitute the sole and exclusive remedy for breach of warranty and the Company shall not be responsible for any incidental special or consequential damages including without limitation lost profits or the cost of repairing or replacing other property which ...

Reviews: