1.  Initial Start-up 

Once the AccUView LED EX has been fitted with the proper 
electrical, air, sample water and drain connections, ensure they 
are tight and leak free. Air and power can now be applied to 
the instrument. Mains connections are supplied only to the Air 
Sentinel III. Turn on power to the Air Sentinel III. Power will be 
supplied to the electronics of the AccUView LED Ex once the Air 
Sentinel III completes a 7 minute purge cycle.  
*Ensure the incoming air line is fitted with the Air Filter/Dryer 
provided

2.  Air Sentinel III Controller Operation  

The Air Sentinel III purge controller is installed on the side of the 
main enclosure. This purge controller will ensure proper, safe 
operation of the AccUView LED Ex. The Air Sentinel III will act 
as a governor to control the power to the rest of the instrument, 
allowing operation only if the correct conditions are met. It does 
this by monitoring air flow and pressure inside the electrical 
enclosure to ensure it meets the minimum requirements. Should 
the air supply fail, the power to the rest of the AccUView LED Ex 
is removed. The AccUView LED Ex will require another seven-
minute purge cycle upon correction of the condition. The Air 
Sentinel III indicates the pressure condition with an LED. If the 
LED is Green, the pressure is fine. If the LED is Red, the pressure 
is too low or not present.

3.  RS-485/4-20mA 

Do not run RS-485 or 4-20mA cables in the same conduit as 
power. Connections are labeled next to the DIN rail connector.

4.  Warm Up 

The AccUView LED Ex requires a 30 minute warm-up period. To 
improve the accuracy, allow the AccUView LED Ex to complete 
warm-up time before calibrating. During the warm-up period, the 
display may flash, indicating that it has detected a temperature 
change. This is normal operation during the warm-up period.

5.  Initial Operation  

The instrument is factory calibrated and can be used straight 
out of the box, however for best accuracy, on site calibration is 
recommended. See owner’s manual for calibration instructions.  
 
Be sure that the cuvette is tightly installed on the flow through unit 
prior to introducing water to the unit. The cuvettes are pressure 
checked at the factory but could have loosened during shipping.

6.  Observe Operation 

All LED lights on the Air Sentinel III should be GREEN, indicating 
proper/normal operation.  

The information contained herein is not intended to replace the 
full product installation and safety information available or the 
experience of a trained product installer. You are required to 
thoroughly read all installation instructions and product safety 
information before beginning the installation of this product.

NOTICE

Q-HF-ACCUViewLEDEx-100128   Rev 0  2008 

 

© 2020 HF scientific

USA:  

T: (239) 337-2116 • Toll-Free (888) 203-7248 • F: (239) 454-0694 • HFscientific.com

Latin America:  

T: (52) 81-1001-8600 • HFscientific.com

Arrow Indicates 

Normal Operation

Measured 

Reading

Measurement 

Scale (%T or ABS)

Screen Display - Normal Operation

100128

Reviews: