Installation, Operation and Maintenance

Pressure Reducing Control Valve with Downstream Surge Control 

Feature

Sizes: 11/4" to 24" 

NOTICE

For Australia and New Zealand: Pipeline strainers should be 

installed between the upstream shutoff valve and the inlet of  

the backflow preventer.

It’s important that this device be tested periodically in compli-

ance with local codes, but at least once per year or more as 

service conditions warrant. If installed on a fire sprinkler system, 

all mechanical checks, such as alarm checks and backflow  

preventers, should be flow tested and inspected internally in  

accordance with NFPA 13 and NFPA 25.

WARNING

!

Read this Manual BEFORE using this equipment.
Failure to read and follow all safety and use information 

can result in death, serious personal injury, property 

damage, or damage to the equipment.
Keep this Manual for future reference.

Table of Contents  

Page

Introduction .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 2

Installation .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 2

Setting the Pressure Reducing Control   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 3

Maintenance Schedule .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 6

Trouble Shooting Guide   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 6

Valve Disassembly Instructions  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 8 

ACV Schematic   .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  . 11

  

Local building or plumbing codes may require modifica-

tions to the information provided.  You are required to  

consult the local building and plumbing codes prior 

to installation.  If the information provided here is not 

consistent with local building or plumbing codes, the 

local codes should be followed.  This product must be 

installed by a licensed contractor in accordance with 

local codes and ordinances.

WARNING

!

Need for Periodic Inspection/Maintenance:

  This product 

must be tested periodically in compliance with local codes, 

but at least once per year or more as service conditions 

warrant .  All products must be retested once maintenance 

has been performed .  Corrosive water conditions and/or 

unauthorized adjustments or repair could render the product 

ineffective for the service intended .  Regular checking and 

cleaning of the product’s internal and external components 

helps assure maximum life and proper product function . 

WARNING

!

Model 910GD-11/610GD-11

IOM-A-ACV-910-11_610-11

Summary of Contents for AMES 610GD-11

Page 1: ...etting the Pressure Reducing Control 3 Maintenance Schedule 6 Trouble Shooting Guide 6 Valve Disassembly Instructions 8 ACV Schematic 11 Local building or plumbing codes may require modifica tions to...

Page 2: ...rom damaging over pressure 1 Prior to installation flush line to remove debris 2 Install valve so the flow arrow matches flow through the line and gauges to monitor valve inlet and outlet pressures A...

Page 3: ...gure 1 If your valve does not include a bleed valve bleed air by loosen ing a fitting on the valve or a plug at the highest point of the valve assembly Step 3 Pressure the line by opening the upstream...

Page 4: ...rol pressure set point by turning the Pressure Reducing Control adjustment screw IN clockwise STEP 2 Adjust the Surge Control by turning the adjustment screw OUT counterclockwise to decrease the downs...

Page 5: ...adjustment screw IN clockwise decreasing the rate of opening See Figure 4 Step 5 If the main valve comes equipped with a closing speed control otherwise ignore this step Closing Speed Needle Valve Ad...

Page 6: ...specification sheets for approximate cover capacity A continuous flow of water from the open port indicates a damaged diaphragm or loose disc diaphragm assembly Disassemble valve and replace diaphragm...

Page 7: ...ly by partially opening from full closed position Improperly configured opening speed control if equipped Adjust opening speed control to verify functionality adjust as required Standard setting for o...

Page 8: ...move cover nuts and washers 3 Remove the cover If cover is not free to be removed loosen it by tapping upward along its outside edge with a dull cold chisel pic tured above a Large valves may require...

Page 9: ...rush or by using a Mineral Dissolving Solution Inspect parts for wear and replace if necessary 7 Inspect valve seat If seat is not damaged removal is not necessary Valve seats 6 and smaller are thread...

Page 10: ...ts in a crossing pattern to ensure even distribution Test the Disc and Diaphragm Assembly for smooth travel by following the Freedom of Movement Test procedure in previous section 11 Test the integrit...

Page 11: ...el 9 Stem Washer ASTM A276 304 Stainless Steel 10 Diaphragm Washer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 11 Diaphragm Buna N Nitrile 12 Disc Retainer ASTM A536 65 45 12 Epoxy Coated Ductile Iro...

Page 12: ...resulting from labor charges delays vandalism negligence fouling caused by foreign material damage from adverse water conditions chemical or any other circumstances over which the Company has no cont...