background image

2

Installation Guidelines

Series 919 and LF919

1

4

" – 2" (8 – 50mm)

Outdoor, Above Ground Installation

For outdoor installations, it is recommended that you install the Series 

919 and LF919 where there are no freezing conditions and above 

ground whenever possible.
You must install the Series 919 and LF919 in an accessible location 

to facilitate testing and servicing. The installation must also allow for 

adequate drainage from the air gap and the discharge line if needed. 

 

WARNING

!

1.   Do not allow the drain line to empty directly into a drainage ditch, 

sewer system, or sump. 

2.   Do not install the Series 919 and LF919 in any location where any 

part of the unit could become submerged in standing water. 

Now available, WattsBox Insulated Enclosures,

for more information, send for literature ES-WB.

FiBERGLASS WattsBox

Min. 12"

Annual inspection of all water system safety and control valves is 

required and necessary. Regular inspection, testing and cleaning 

assures maximum life and proper product function.

Outdoor Installation

Parallel Installation

Watts

1

4

" – 2"  

(8 – 50mm) 

919AQT

Watts

1

4

" – 2" 919

(8 – 50mm)

A.

   Shutoff Valves: If you remove the shutoff valves from the Series 

919 and LF919, reassemble the shutoff valve with the test cock 

mounted on the inlet side of the unit. 

B.

   Always install the Series 919 and LF919 in an accessible location 

to facilitate testing and servicing (See Page 1). 

*Check the state 

and local codes to ensure that you install the backflow pre-

venter in compliance with those codes, such as the proper 

height above the ground.

 

C.

   It is recommended that you install a strainer ahead of the Series 

919 assemblies to protect the internal components from unnec-

essary fouling. 

 

CAUTION

!

Do not install a Series 919 and LF919 with a strainer in rarely used 

water lines, such as a fire sprinkler system which is only used during 

emergencies. 
Start Up:  Close the downstream shutoff. Open the upstream slowly 

and fill the valve. When the valve is filled, open the downstream 

shutoff slowly, and fill the water supply system. This is necessary to 

avoid water hammer and/or shock damage. 

D.

   Vent the air gap and drain line from the relief valve in accordance 

with code requirements. Terminate discharge  approximately 12" 

(300mm) above the ground or through an air gap piped to a floor 

drain.

 

WARNING

!

Do not allow the drain line to empty directly into a drainage ditch, sewer 

system, or sump.

 

NOTICE

Relief Valve Discharge Rates
The Series 919 and LF919 air gap and drain line terminating above 

a floor drain can accommodate any moderate discharge or nuisance 

spitting through the relief valve. However, to prevent water damage 

in the case of a catastrophic failure, you may need to design the 

floor drain size to accommodate the increased discharge.  Refer to 

Figure 1 for maximum relief valve discharge rates, size, and capacity 

of typical floor drains. 

 

NOTICE

DO NOT reduce the size of the drain line from the air gap fitting. The 

drain line must remain at full line size.

E.

   After initial installation of the Series 919 and LF919, a discharge 

from the relief valve may occur due to dirt and pipe compounds.  

This may be due to inadequate initial flushing of the pipe lines. If 

flushing the valve does not clear the unit, remove the first check 

valve and clean thoroughly, using the procedures in "Servicing 

First & Second Check Valves" on Page 4. 

 

NOTICE

Periodic relief valve discharge may occur on dead end service applica-

tions, such as boiler feed lines or cooling tower makeup lines. This may 

be due to fluctuating supply pressure during a static or no flow condi-

tion. To avoid this discharge, install a spring-loaded, rubber seated 

check valve ahead of the backflow assembly. 

F. 

 It is recommended that you not place the Series 919 and LF919 

in a pit or at a depth below the ground level, unless absolutely 

necessary.  If an installation requires below ground level instal-

lation, a modified pit installation is recommended, as well as 

the approval of local codes. In such cases, provision should be 

made to always vent the drain line above the flood level.  In the 

case of a pit drain, ensure an adequate air gap exists between 

the bottom of the drain line and the bottom of the pit.

G.

   It is recommended that periodic inspection of the Series 919 and 

LF919 be done to check for any discharge from the relief valve. 

This discharge is a visual indication that the valve needs cleaning 

or repair. In addition, it is recommended that periodic testing of 

the valve be done in compliance with local codes to ensure its 

proper operation.

Min. 12" (300mm)

Parallel Installation

For parallel installations, you can install two or more small sized 

Series 919's and LF919's (when approved) to serve a large sup-

ply pipe main. You can use this type of installation in an application 

where increased capacity beyond that provided by a single valve is 

required. Additionally, this type of installation permits testing and/or 

servicing of a single valve without shutting down the complete line.
The number of Series 919 and LF919 units installed in parallel should 

be determined by the engineer's judgement, based on the operating 

conditions of a specific application.

 

NOTICE

The total capacity of all the units installed in the application should 

equal or exceed that required by the system.

Reviews: