Watson McDaniel Company UTS600 Manual 2590000 RevA
Start-Up
1.
Upon start-up, the blowdown valve should be in the open position. Outlet isolation valve and test valve should
be in the closed position. When opening blowdown valve, hold blowdown valve body in place with wrench
while opening valve head.
2.
Open the inlet isolation valve to blowdown and purge the trap station.
3.
Once the trap station is blown down, close blowdown valve.
4.
Open outlet isolation valve. Trap station is now in operation.
Maintenance
1.
To clean strainer, open blowdown valve to clear any debris. When opening blowdown valve, hold blowdown
valve body in place with wrench while opening valve head.
2.
To test the trap for proper operation, open the test valve during normal operation and close the outlet isolation
valve. Observe the discharge from the test valve. If condensate and flash steam is discharging, trap is working
properly. If live steam is present, trap may be failed open. If no condensate is present, trap may be failed
closed. Replace trap module if necessary. Do not remove trap until pressure is relieved and trap is cool. Refer
to trap installation and operation manual for further trap operation detail.
3.
If trap module needs to be removed, isolate the trap by closing the inlet and outlet isolation valves. Open the
blowdown valve and test valve to relieve the pressure and drain any condensate. Once pressure is relieved and
trap is cool, the trap can now be removed and replaced.
Note: When opening blowdown and test valve, hold the valve body in place at the base, with a wrench, while
opening valve head.