HIGHGATE
Pressure Balance Control Valve Trim
INSTALLATION GUIDELINES
Page 2 of 3
6.5.2012
These guidelines have been prepared for the professional contractor to aid in the installation of:
HIGHGATE PRESSURE BALANCE TRIM WITH PORCELAIN LEVER HANDLE (STYLE# HGPB10)
All dimensions are based on original specification and are subject to change and variation.
Please consult your Design Associate for current specifications.
HOT LIMIT SAFETY STOP CALIBRATION:
¾
IMPORTANT: The Pressure Balance Valve is
equipped with a hot limit safety stop screw to limit
the valve handle from being turned to excessive hot
water discharge temperatures.
4.
Remove the dome cover and open the valve to the
maximum desired temperature verified with a
thermometer and turn the safety stop screw
clockwise until it seats. WARNING: Failure to adjust
the hot limit safety stop screw properly may result
in serious scalding.
Figure - 02
Dome Cover
Safety Stop Screw
TRIM INSTALLATION:
5.
Screw the nose cone (7) onto the packing nut until
fully seated.
6.
Slide the trim plate (10) over the nose cone (7) and
attach it to the valve with the screws (8) provided. If
it is difficult to slide the plate over the nose cone,
moisten the o-ring (9) inside the plate.
7.
Remove indice (1) from the handle (5) to remove the
screw (3) and washer (4).
8.
Slide the nose cone cap over the valve stem then
attach the handle to the stem using the screw (3)
and washer (4).
9.
Re-insert the indice into the handle.
¾
If further assistance is required, please contact
Product Support at 1-800-927-2120 (9am-6pm EST).