background image

Step 3

 

Place the left gable onto the floor 

 

and secure at the corner with 

 

3x50mm screws.

 

Fix to the floor using 2x50mm screws,

 

ensure to screw through the framing

 

into the floor bearers.

5x50mm Screws

Pre drill 

hole

50mm 

screw

a

b

Step 3

Fix the front panel inbetween the gables,

securing into place with 4x50mm screws

from the inside of the building.

*Ensure to align the framing with the edge

of each gable.

4x50mm Screws

Pre drill 

hole

50mm 

screw

8

8

Step 4

Attach the door strips to either side of the

building.

*Ensure the strip sits fush to edge of the

framing and there is NO overhang inside

the building.

6x30mm Screws

11

Step 5

Fit 2x butt hinges to each door with

3x30mm screws per hinge.

Align each door into the door gap

and secure into place with 3x30mm

screws per hinge.

*Ensure the doors open and close

freely without any obstructions.

24x30mm Screws

P 3

Please retain product label and instructions for future reference

             

a

b

2

b

a

a

1

Pre drill 

hole

30mm 

screw

Pre drill 

hole

30mm 

screw

Reviews: