background image

R-1: March 17, 2018 
 

 
 
 
 

 

4. Airlock / Rotary Valve 

o

  The airlock package comes equipped 

with a Walinga 1210 drop-thru airlock. 
It is built as a single assembly.

 

o

  The airlock will be placed under the 

cyclone assembly and above the 
customer’s discharge option. 

o

  Discharge piping is 6” and should be 

installed vertically with a maximum of 
a 20° slope. This ensures that dust 
will flow through the spouting using 
only gravity. 

o

  The airlock operates off of an electric 

motor and chain drive and has to be 
placed in an easily accessible location for service. 

o

  The dimension of the airlock package is 27-½” long by 28” 

wide. 

 
 

 

5. Blower Package 

o

  The blower package comes 

equipped with a Walinga PD Blower. 
It is used to generate the suction of 
the system. The blower package 
frame is a heavy-duty steel frame.

 

o

  The base itself is 32” wide by 43–

3/8” long for the standard 614 
blower. (31-½” wide by 41-½” long 
for the 510 blower base) 

o

  The blower package has a single 6” 

port where the air stream is 
generated. 

o

  The 6” pipe going into the blower 

inlet, comes from the receiver top 
section. 

o

  The blower is a crucial part of the 

Central-Vac system and requires 
regular service. 

o

  When installing, ensure that the belt 

cover and the blower are easily 
accessible for the service personnel.

Fig 4. Airlock Package 
 

Fig 5. Blower Package 
 

Summary of Contents for CENTRAL-VAC AIR-PURGE

Page 1: ...R 1 March 17 2018 CENTRAL VAC AIR PURGE INSTALLATION MANUAL...

Page 2: ...artment Fax 519 824 0367 Manitoba and Western Canada Chad Yeo 204 745 2951 ext 424 chad yeo walinga com USA John VanMiddlekoop 800 466 1197 ext 3 jvm walinga com SALES MANAGER Tom Linde 519 787 8227 e...

Page 3: ...re that the Central Vac is anchored to firm and level ground Make certain that sufficient amperage at the proper voltage and frequency 60Hz is available before connecting power for the electric model...

Page 4: ...R 1 March 17 2018 Components of a Central Vac Air Purge System...

Page 5: ...m the airstream o The receiver midsection is the portion of the receiver that is to bolted to the Cyclone Assembly o Install with care ensuring there is no damage to the explosion vent 3 Receiver Top...

Page 6: ...he dimension of the airlock package is 27 long by 28 wide 5 Blower Package o The blower package comes equipped with a Walinga PD Blower It is used to generate the suction of the system The blower pack...

Page 7: ...R 1 March 17 2018 Typical Machine Setup...

Page 8: ...with a 3 mainline and 2 drop lines Galvanized steel elbows o Used for corners in the piping system o Available in 2 3 4 and 6 o 6 elbows are utilized between the blower filter housing and separators o...

Page 9: ...e o Ground strip is put into place in order to prevent static electricity build up Mounting Brackets o The mounting brackets are mounted to the wall or to any other solid support o The saddle clamps a...

Page 10: ...d of the central vac system and is used by the operator o The flex line has a static wire built into it to prevent static electricity build up If servicing a rubber hose ensure that the ground wire is...

Page 11: ...event connection leaks o When installing a camlock coupling be sure to apply a ring of silicone around the piping and have the dust plugs inserted and clamped in place o By having the dust plugs inser...

Page 12: ...should the system become plugged o One support point for every 15 of pipe line is recommended Ensure that the main lines are as straight as possible to maintain maximum conveying rate Space the inlets...

Page 13: ...s to ensures total protection from static electricity build up as the grounding strip is connected to both pipes As much as possible ensure that all joining components are easily accessible for any fu...

Page 14: ...r mid section and receiver top to the cyclone assembly Ensure that the explosion vent is positioned in the correct direction towards ducting or outlet on the wall If a change to the orientation of the...

Page 15: ...installation unique Refer to the system design drawing for every install Dust free 2 cubic yard dust bin which can be installed under the discharge A selection of different electrical options are ava...

Page 16: ...Board Power Connection to be wired between terminal 7 and 2 Voltage 120VAC 3 High Level Sensor a High Level Sensor Normally open to be wired between terminal 8 and 3 Voltage 120VAC 4 Auxiliary Stop Se...

Reviews: