Drawing A. Installation as oversink model
The device must be installed as shown in the installation drawing (A) for oversink
model on the first page of this manual.
• Left outlet of the device is the water outlet (hot/ red), right outlet is the
water inlet (cold/ blue).
• Prepare the water connections to the tap. Make sure main water supply
is switched off.
• Prepare the electrical connections for the device. For the 4.5 kW and 5.5
kW: Make sure main power is switched off.
• To prepare the connection to the water supply Teflon tape must be used
for sealing the pipes.
• Mount the tap to the main water supply.
• Level the tap horizontally.
• Mount the device to the tap.
• Open the main water supply and check for leakage and release air from
the system by opening the hot water tap.
• 3.5 kW: When air has left the system, plug in the device to the electric system.
4.5 and 5.5 kW: When air has left the system, connect the device to the
electric system.
• Heater should now function!
Drawing B. Installation as undersink model
The device must be installed as shown in the installation drawing (B) for under-
sink model on the first page of this manual.
• Left outlet of the device is the water inlet (cold/ blue), right outlet is the
water outlet (hot/ red).
• Prepare the water connections to the tap. Make sure main water supply
is switched off.
• Install the device by using the plastic installation bracket which is supplied
with the device. For the 4.5 kW and 5.5 kW: Make sure main power is
switched off.
• Connect the water supply to the device and to the main water supply.
• Open the main water supply and check for leakage and release air from
the system by opening the hot water tap.
• 3.5 kW: When air has left the system, plug in the device to the electric system.
4.5 and 5.5 kW: When air has left the system, connect the device to the
electric system.
• Heater should now function!