WAGO WINSTA® 770
Connect Devices
29
770-629/130-000 WINSTA® Sunblind Box 4 Channel
Manual
Version 1.1.1, valid from HW/FW version XXXX0201XX
Pos: 53 /Alle Serien (Allgemeine Module)/Überschriften für alle Serien/Anschlussbeispiele - Überschrift 2 @ 4\mod_1240996036328_21.doc @ 32010 @ 2 @ 1
6.1
Connection Examples
Pos: 54 /Serie 770 (Winsta-Boxen)/Anschließen/Anschlussbeispiele/Anschlussbeispiele 0770-0629/0130-0000 @ 6\mod_1260444240884_21.doc @ 46973 @ 3443 @ 1
6.1.1
Central Connection with 24V Signals (Central Operation)
6.1.1.1
Central Operation without Voltage Monitoring
On principle, the configuration of a central operation (e.g. central switch, timer)
should take place according to the following scheme.
L / N / PE
230 V
AC
24 V
DC
Central Connection Standard
Central Control
GND
up
down
Figure 11: Wiring of the Winsta sunblind boxes for conventional 24 V control
In central operation without voltage monitoring, 24V levels are evaluated as a
control signal.
Heed the line dimensioning!
For the wiring of a system with central control, make sure that the dimensioning
(length and cross-section) of the control line is made according to the boxes
connected.
Setting of the DIP Switches
Switch 4 of DIP Module 2 must be de-activated for operation without voltage
monitoring.