![Wacker Neuson LTV6L Operator'S Manual Download Page 39](http://html1.mh-extra.com/html/wacker-neuson/ltv6l/ltv6l_operators-manual_3153770039.webp)
wc_tx004430gb_FM10.fm
39
LTV
Machine Setup
4.4
Leveling the Trailer—Vertical Mast Light Towers
Procedure
Perform the procedure below to level the trailer.
1. Pull the locking pin on the tongue jack
(a)
and rotate the tongue jack down 90°
as shown. Reinsert the pin once the jack is in position.
2. Block or chock the trailer wheels
(b)
.
3. Crank the tongue jack
(a)
down to raise the trailer tongue off the vehicle.
4. Pull the outrigger lock pins
(c)
to release the outriggers. Pull both outriggers
(d)
out until you feel the lock pin snap into place.
5. Pull the locking pins on the outrigger jacks
(e)
.
Rotate the jacks down 180°.
Reinsert the pins once the jacks are in position.
6. Extend the jack(s) on the highest side(s) of the trailer until they rest firmly on the
ground. Extend the remaining jacks until the trailer is level.
WARNING
Tipping and falling hazard. Failure to level the trailer or extend the outriggers will
reduce the stability of the unit.
►
Level the trailer and extend the outriggers before raising the tower. The
outriggers must remain extended while the tower is up.
a
e
d
b
c
c
d
e
wc_gr013324
Summary of Contents for LTV6L
Page 8: ...Table of Contents LTV wc_bo5100030216_02_FM10TOC fm 8 ...
Page 21: ...wc_si001039gb_FM10 fm 21 LTV Labels wc_gr013743 W W V T U Q S ...
Page 108: ......
Page 110: ......