6.1
Towing the machine
Important information regarding towing
WARNING
Accident hazard due to towing!
Can cause serious injury or death.
►
The machine may only be towed using suitable towing equipment
(towing bar or cable) in connection with suitable towing facilities, such
as a towing coupling, hooks and eyes.
►
Start machine travel and tow away slowly.
►
Ensure that no one is between the vehicles during towing.
►
Have a recovery service or a Wacker Neuson service center tow the
machine away if necessary.
►
See chapter “Safety, section 2.8”.
►
Ensure that no one is near the towing bar or cable. The lateral safety
distance is equal to 1.5 times the length of the towing equipment.
NOTICE
Only tow the machine if absolutely necessary.
►
Tow away the machine only if the engine is running and if the drive is
functional. A malfunctioning machine must be loaded with a crane.
►
If necessary, contact a Wacker Neuson service center for towing the
machine away.
►
Fasten the towing equipment only on the towing eye provided for this.
►
The maximum permissible load of the towing eye hook is equal to 1.5
times the maximum weight of the machine.
►
A tractor vehicle of the same weight category must be used as a
minimum.
In addition, the tractor vehicle must be equipped with a safe braking
system and sufficient tractive power.
Summary of Contents for ET12 02
Page 8: ...EG 4 BA ET18 20 24 en 1 5 et18_20_24konf fm Declaration of conformity Notes...
Page 16: ...1 8 BA ET18 20 24 en 1 5 et18_20_24v100 fm 1 Foreword Notes...
Page 48: ...3 12 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction Warning labels Cabin Canopy...
Page 53: ...BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 17 Introduction 3 Information labels...
Page 60: ...3 24 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction...
Page 104: ...4 44 BA ET18 20 24 en 1 5 et18_20_24i400 fm 4 Putting into operation...
Page 118: ...5 14 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation...
Page 170: ...5 66 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation Notes...
Page 178: ...6 8 BA ET18 20 24 en 1 5 et18_20_24t600 fm 6 Transport...
Page 230: ...7 52 BA ET18 20 24 en 1 5 et18_20_24w710 fm 7 Maintenance Notes...
Page 280: ...9 48 BA ET18 20 24 en 1 5 et18_20_24t900 fm 9 Technical data Notes...