CP-1605
Important notes For the Installer
A Quick Check List
Are the water connections to the water heater oriented in a way to
avoid trapping air in the heating circuit? (see diagram on next page)
Is the purge valve installed on the return line from the air handler
upstream from the isolation valve?
Is the air handler hung and isolated to avoid transmitting vibration
through framing and duct work? Or is the air handler on a
housekeeping pad?
Are the isolation valves full-port? Restrictive valves will limit
performance.
Are Thermostat connections correct, including cooling and continuous
run connections?
Have the packing materials been removed from the blower and the
pump ?
Is there an installation manual for the home owner ?
Is the unit accessible? Are there clearances for service and component
replacement?
Are the supply plenum and return duct/drop acoustically lined ? (at
least 6ft. of the return duct/drop and the supply plenum are
recommended)
Is the filter cover in place? Is a clean filter in place? Is the supplied
filter rack installed?