background image

5786 832 - 03     03/2018

Please file in Service Binder

Refer to the Installation Instructions applicable 

to this boiler.

Do not perform service work on any component part 

without ensuring safe operation of the heating system. 

When replacing parts, use original Viessmann or 

Viessmann approved replacement parts.

Safety and Installation Requirements

Please ensure that these instructions are read and 

understood before starting any service work. Failure to 

comply with these instructions may cause product/property 

damage, severe personal injury and/or loss of life.

Working on the equipment

The installation, adjustment, service and maintenance of 

this product must be performed by a licensed professional 

heating contractor who is qualified and experienced in 

the installation, service, and maintenance of hot water 

boilers. There are no user serviceable parts on the boiler, 

burner or control.

Ensure that main power to the equipment being serviced 

is off.
Ensure that the main fuel supply valve to the boiler is 

closed.
Take precautions to avoid accidental activation of power 

or fuel during service work.

for use with: Vitocrossal 300 CA3 / CA3B

Unpacking the CA3 Boiler

 

1

Unscrew back panel. 

2

.  

The remaining packaging parts are screwed together. 

Open the packaging parts in the following order:

 

Front panel

 

Top panel

 

Left side panel

 

Right side panel

Boiler Lifting Instructions

for use by heating contractor

Note:

 The boiler can be lifted by crane only while it is still

 packed. 

1.   Remove plastic covering.
2.   Dismantle the wooden packaging framework.

3.   Lift the boiler form the packaging platform using a

 

pallet or forklift truck. Use fork extensions. Observe

 the 

weight.

Unpacking the CA3B Boiler

 

Summary of Contents for Vitocrossal 300 CA3

Page 1: ...experienced in the installation service and maintenance of hot water boilers There are no user serviceable parts on the boiler burner or control Ensure that main power to the equipment being serviced is off Ensure that the main fuel supply valve to the boiler is closed Take precautions to avoid accidental activation of power or fuel during service work for use with Vitocrossal 300 CA3 CA3B Unpacki...

Page 2: ...welds shall have 100 magnetic particle inspection MPI 9 Shackle pins to be minimum 1 25 4 mm dia Structural steel 1 Structural steel shall conform to the latest edition of S16 09 and the CISC code of standard practice 2 Structural steel shall conform to CSA G40 21 300W G40 21M 350W class C for H S S and G40 21M 350W for W shape sections 3 All plates and round bars to be A44 300 MPa material minimu...

Page 3: ...ropes are correctly hooked operate the crane to lift the boiler It is essential to use appropriate lifting devices certified of lifting to a minimum of the boiler weight WARNING If flue gas connection is damaged leakage may occur Do not lift boiler at the flue gas connection The lifting should be performed by a trained technician When lifting take sufficient safety measures and proceed with great ...

Page 4: ... and recyclable paper Positioning boiler The boiler must be placed on a foundation A minimum height of 4 in 100 mm is required in order to allow for the condensate siphon connection Positioning the Boiler Boiler Lifting Instructions For more detail refer to the Installation Instructions applicable to this boiler ...

Reviews: