131
A
B
C
Fig. 106
1.
Shut off and drain the boiler on the heating water
and DHW sides.
2.
Release side fasteners and pivot control unit for-
ward.
3.
Remove the trap (see page 57).
4.
Extract thermal insulation
A
and remove it.
5.
Undo two screws
B
and remove plate heat
exchanger
C
by pulling forwards.
6.
Check the connections on the heating water and
DHW side for soiling and scaling; if required,
replace the plate heat exchanger.
7.
Install in reverse order using new gaskets.
Checking the flue gas temperature sensor
The flue gas temperature sensor locks out the boiler if
the permissible flue gas temperature is exceeded.
Reset the interlock after the flue system has cooled
down by pressing reset
R
.
Troubleshooting
Repairs (gas condensing module)
(cont.)
5775 636 GB
Diagnosis
Summary of Contents for C3TB
Page 136: ...136 Troubleshooting Repairs gas condensing module cont 5775 636 GB Diagnosis ...
Page 143: ...143 Parts lists Heat cell assembly 5775 636 GB Components ...
Page 160: ...160 Parts not shown 0009 PCB IU100 B30 Parts lists Fuel cell assembly 5775 636 GB Components ...
Page 161: ...161 Parts lists Fuel cell assembly cont 5775 636 GB Components ...
Page 187: ...187 5775 636 GB ...