80
4.
Check the CO
2
content. Should the
actual value deviate from the above
ranges, implement steps from page
79.
5.
Record the actual value on
page 184 of the commissioning/
service report.
6.
Adjust
"Eng + Supp bu max"
(see
page 80).
7.
Check the CO
2
content. Should the
actual value deviate from the above
ranges, implement steps from page
79.
8.
After testing, press
d
.
9.
Record the actual value on
page 184 of the commissioning/
service report.
Setting the heating output
1.
If necessary, press "ESC" repeat-
edly, until the default display is
shown.
2.
Press "
Ð
"; this activates the emis-
sions test function (see page 160).
3.
Press "OK".
"Eng burner min"
flashes on the dis-
play.
4.
Select the individual output settings
with rotary selector "
J
":
■
"Eng burner min"
(Stirling burner
minimum)
■
"Eng + Supp bu max"
(Stirling &
auxiliary burner max)
5.
Confirm with "OK".
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5618 294 GB
Summary of Contents for C3HA
Page 39: ...39 2 2x 1 Installation sequence Removing the front panel 5618 294 GB Installation ...
Page 42: ...42 1 2 Installation sequence Removing the transport brackets 5618 294 GB ...
Page 151: ...151 Checking and replacing resistors B C A Troubleshooting Repairs cont 5618 294 GB Service ...
Page 181: ...181 Parts lists Control unit assembly cont 5618 294 GB Service ...
Page 183: ...183 Parts lists Miscellaneous assembly cont 5618 294 GB Service ...
Page 191: ...191 5618 294 GB ...