system_integration:hub4_grid_parallel https://www.victronenergy.com/live/system_integration:hub4_grid_parallel?rev=1456310763

https://www.victronenergy.com/live/

Printed on 2020-12-11 00:44

single phase setup diagram:

Note the jumper between terminals 1 and 4.

Meter configuration

Change the front selector of the AC sensor so it is not in the locked state. This will allow the CCGX to
automatically configure the meter. The front selector is located next to the display as indicated in the
image below.

Summary of Contents for Hub-4

Page 1: ...gy is stored in the battery And that stored energy is then to power the loads at times when there is a shortage of PV power The system is managed by the Color Control GX CCGX which also provides exten...

Page 2: ...bility is given to implement time shifting load management or other energy management optimization algorithms Either by ModbusTCP commands or by running additional self implemented code on the Color C...

Page 3: ...ample the EM24DINAV53DISX which uses Current Transformers and can therefore work in systems 63A per phase Note that this model is not stocked by Victron Energy we recommend to purchase it locally 2 Ba...

Page 4: ...nly one phase and compensate on that phase for the other two phases thereby e ectively regulating the total power of all three phases combined See the following example where the Hub is connected to L...

Page 5: ...sate for the shortage Multis on phases with a net power production will be on idle Disabling phase compensation In a hub 4 system it is still possible to balance the grid power of each phase to 0W Dis...

Page 6: ...ww victronenergy com live Printed on 2020 12 11 00 44 single phase setup diagram Note the jumper between terminals 1 and 4 Meter con guration Change the front selector of the AC sensor so it is not in...

Page 7: ...USB converter to the CCGX using the supplied USB cable A few seconds after connecting the active LED should be on and the TX RX LED should be blinking the converter takes its power from the CCGX so th...

Page 8: ...onverter Grid meter Yellow Terminal 41 Orange Terminal 42 Black Terminal 43 The Red Green and Brown wire are not used 5 Multi Quattro installation and con guration First follow the instructions as per...

Page 9: ...entered as soon as the battery is discharged see above During Sustain Mode the batteries will slowly be charged from the grid maximum charge current is 5 Amp re The Sustain level is 12 5V for lithium...

Page 10: ...he display will come to life If not check the wiring of the system 2 Within 60 seconds after power up the CCGX will detect the meter The meter will show up in 3 the device list on the display When sel...

Page 11: ...sing terminals 3 6 and 9 Now you can chose on which phase you want the PV inverter by connecting the L1 line of the PV inverter to terminal 1 4 or 7 There are 3 options to connect the extra AC sensor...

Page 12: ...sensor to measure both grid and PV inverter For wiring see the diagram below On the CCGX go to the grid meter in the Wired AC sensor settings Make sure Phase type is set to Single phase and PV invert...

Page 13: ...n xxyy403 I get a lot of Low battery pre alarm warnings Solved by updating to xxyy403 or higher Does Hub 4 work for parallel systems Yes Hub 4 works for systems where multiple Multis or Quattros are i...