Vertiv
|
NetSure 710 Series Installation Manual (IM581127000)
|
Rev. U
92
Connecting Converter Output Cables 581127000 List 60
NOTE!
These connections are factory made for shelves factory installed. The connection must be
made if a field expansion shelf is installed.
Connecting List 60 Converter Output Cables to List DA, DB, DC, DD, DE, DF, DG, DH, DJ, and DK
Distribution Panel
Procedure
1.
Locate the output jumpers (labeled -48V) supplied with List 60 (P/O kit P/N 540860). There are two
(2) cables per List 60.
2.
Open the distribution cabinet’s front door by turning the latch in the counterclockwise position.
3.
Loosen the screws holding the plastic shield over the circuit breakers or fuseholders on the dual voltage
distribution panel. Slide the shield upwards and remove.
4.
Connect the output jumpers to the distribution bus panel subsystem (-48V) input terminals as shown in
. Apply electrical anti-oxidizing compound to lug mating surfaces before connecting. Mount
two lugs back-to-back per mounting position if required. Torque as shown in the figure.
5.
Route the output jumpers installed in the previous step over the top of the distribution bus panel ground
bar, toward the back of the cabinet, and down through the opening in the bottom of the distribution
cabinet (between the cabinet main busbars).
6.
Route the output jumpers to the converter output terminals as shown in
7.
Connect the output jumpers to the converter output terminals as shown in
. Apply electrical
anti-oxidizing compound to lug mating surfaces before connecting. Torque as shown in the figure.
8.
Install the plastic shield that was removed in a previous step, over the circuit breakers or fuseholders.
To do so, position the shield and slide downwards on screws. Tighten screws.