Mechanical Installation
29
2.10. Mechanical Installation Checklist
Initiate the inspection checks after the mechanical installation is completed. Pre-check and confirm that there are no
discrepancies or faults. Ensure that all the points in the checklist (refer
for installation checklist) are complying
accordingly..
Table 2-14 Mechanical Installation Checklist
Check Items
Results
Leave enough space around the installed unit to facilitate unit maintenance.
The unit is placed vertically, and the installing fasteners are firmly fixed.
The piping connecting the indoor and outdoor units have been installed properly, and the ball
valves of the condenser, the Liebert XDC unit, and the terminal have been fully opened.
The cold drain pipe at the cooling terminal is firmly connected.
All piping joints are tightened and leak proof.
All supporting fasteners used for transportation have been removed.
After the unit is installed, the debris inside or around the unit has been removed (such as
transportation materials, mechanical parts, materials, tools, etc.)
Everything is checked and verified, follow the electrical installation.