3 PRE-INSTALLATION PREPARATION AND GUIDELINES

NOTE: Before installing unit, determine whether any building alterations are required to run piping,

wiring and ductwork. Follow all unit dimensional drawings and refer to the submittal engineering

dimensional drawings of individual units for proper clearances.

Refer to

PFD Model Number Nomenclature

on page 7, and submittal drawings to determine the type of

system being installed and anticipate building alterations, piping and ductwork needed.

The unit dimensions, pipe-connection locations, and piping schematics are described in the submittal

documents included in the

Submittal Drawings

on page 35.

Allow at least the minimum recommended clearances maintenance, and service. See the

appropriate submittal drawings for dimensions.

Be mindful of the placement of the PFD in relation to the connected evaporator unit, other

outside units, barriers, and walls for air flow clearance, equivalent piping distances, and

differences in elevation between the PFD and connected evaporator unit.

When applications do not meet or exceed any of these specifications, contact your Vertiv

representative.

3.1 Planning Dimensions

The unit dimensions described in the submittal documents included in the

Submittal Drawings

on

page 35.

The following table lists the relevant documents by number and title.

Document Number

Title

Outdoor Condensing Unit

DPN004058

Cabinet dimensions, 5-ton, top discharge

DPN004063

Cabinet dimensions, 3-, 4-, and 5-ton, horizontal discharge

DPN004066

Optional anchoring plan, 3-, 4-, and 5-ton, horizontal discharge

Table 3.1 Dimension Planning Drawings

3.1.1 Location Considerations for Outdoor Condensing Unit

Observe the following when planning the installation of the outdoor unit:

To ensure a satisfactory air supply, locate air-cooled condensing units in an environment with

clear air, away from loose dirt and foreign matter that may clog the coil.

Condensing units must not be located in the vicinity of steam, hot air or fume exhausts or

closer than 18 inches from a wall, obstruction or adjacent unit.

For multiple-unit installations, space the units so that the hot, condensing-unit exhaust air is

not directed toward the air inlet of an adjacent unit.

Avoid areas where heavy snow will accumulate at air inlet and discharge locations.

The condensing unit should be located for maximum security and maintenance accessibility.

Avoid ground-level sites with public access. Install a solid base, capable of supporting the

weight of the condensing unit.

The base should be at least 2 in. (51 mm) higher than the surrounding grade and 2 in. (51 mm)

larger than the dimensions of the condensing-unit base. For snowy areas, a base of sufficient

height to clear snow accumulation must be installed.

Before beginning, refer to

Piping and Refrigerant Requirements

on page 11 for unit placement, piping

guidelines, and refrigerant-charge requirements for your system.

The condensing unit must be located within the maximum distance from evaporator per the guidelines

listed in

Pipe length and condenser elevation relative to evaporator

.

3 Pre-installation Preparation and Guidelines

9

Summary of Contents for Liebert PFD

Page 1: ...Liebert PFD Prop Fan Digital Condensing Unit Thermal Management Systems Installer User Guide...

Page 2: ...ims all liability for damages resulting from use of this information or for any errors or omissions Refer to other local practices or building codes as applicable for the correct methods tools and mat...

Page 3: ...gerant line Sizes and Equivalent Lengths 14 4 2 1 Refrigerant Charge Requirements 14 4 2 2 Additional Oil Requirements for Digital scroll Compressors 19 5 Electrical Connection Requirements 21 5 1 Low...

Page 4: ...Vertiv Liebert PFD Installer User Guide 4...

Page 5: ...h pressure refrigerant loss of refrigerant environmental pollution equipment damage injury or death This unit contains fluids and gases under high pressure Use extreme caution when charging the refrig...

Page 6: ...ration system Maintaining system cleanliness is extremely important because the oil will tend to bring any foreign matter back to the compressor NOTICE Risk of improper refrigerant charging Can cause...

Page 7: ...compressor Digit 4 Sound level 0 Standard Z Quiet Line 067 models only Digits 5 and 6 NominalCapacity 1 000 BTU hr Digit 7 Unit type A Air cooled Digit 8 Coiltype Standard coil C Coated coil Digit 9 S...

Page 8: ...ittal documents included in the Submittal Drawings on page 35 The following tables list the relevant documents by number and title Document Number Title DPN004180 PFD Condensing Unit 3 4 and 5 ton Tab...

Page 9: ...3 4 and 5 ton horizontaldischarge DPN004066 Optionalanchoring plan 3 4 and 5 ton horizontaldischarge Table 3 1 Dimension Planning Drawings 3 1 1 Location Considerations for Outdoor Condensing Unit Obs...

Page 10: ...ing and moving equipment is rated for the weight of the unit before attempting to move lift remove packaging from or prepare the unit for installation Unit weights are specified in Table 3 2 above CAU...

Page 11: ...sive discharge of high pressure refrigerant loss of refrigerant environmental pollution equipment damage injury or death This unit contains fluids and gases under high pressure Use extreme caution whe...

Page 12: ...low of dry nitrogen through the piping during brazing to prevent formation of copper oxide scale inside the piping When copper is heated in the presence of air copper oxide forms POE oils will dissolv...

Page 13: ...frigerant line Sizes and Equivalent Lengths on the next page for recommended refrigerant piping sizes based on equivalent pipe lengths Refer to Refrigerant Charge Requirements on the next page for the...

Page 14: ...e in 1 2 1 2 5 8 5 8 5 8 MT060HE PFD067A L Suction line in 1 1 8 1 1 8 1 1 8 1 1 8 1 1 8 Liquid line in 1 2 5 8 5 8 5 8 5 8 MT060HE PFDZ67A L or PFD067A H Suction line in 1 1 8 1 1 8 1 1 8 1 1 8 1 1 8...

Page 15: ...1 1 0 Source DPN003099 Rev 1 Table 4 6 Interconnecting piping refrigerant charge for R 410A lb per 100 ft kg per 30 m Model Charge lb kg PFD037A L1 13 4 6 1 PFD037A H1 27 12 2 PFD054A L1 27 12 2 PFD06...

Page 16: ...ve the solenoid valve holding coilthen apply solenoid valve service magnet to the valve 4 Externalequalizer 5 Sensing bulb 6 Suction pressure transducer 7 Suction line 8 Schrader port with valve core...

Page 17: ...initial deep vacuum of 500 microns on the system with a suitable pump 4 After 4 hours check the pressure readings and if they have not changed break vacuum with dry nitrogen Pull a second and third va...

Page 18: ...r restricted air flow 3 Below design ambient temperatures refrigerant backs up into the condenser coil and the charge level drops below the sight glass At lower ambient temperatures block the condense...

Page 19: ...at the suction side of the system while the system is running Model PFD037 PFD054 PFD067 PFDZ67 Refrigerant System Charge per Circuit lb kg Additional Oil Required Per Circuit oz ml 40 18 1 0 0 0 40...

Page 20: ...Vertiv Liebert PFD Installer User Guide 20 This page intentionally left blank...

Page 21: ...ore turning power On Check all electrical connections periodically and tighten as necessary NOTICE Risk of improper electrical connection of three phase input power Can cause backward compressor rotat...

Page 22: ...supplied shielded 6 wire control connection 24 VAC is required between the evaporator and the condensing unit Control wiring must be installed in accordance with the National Electrical Code NEC Clas...

Page 23: ...al tag 9 Power wiring connections completed including earth ground 10 Power line circuit breakers or fuses have proper ratings for equipment installed 11 Control wire to condensing unit is shielded co...

Page 24: ...Vertiv Liebert PFD Installer User Guide 24 This page intentionally left blank...

Page 25: ...oper electrical connection of three phase input power Can cause backward compressor rotation and unit damage Service technicians should use a gauge set on the system during the initial start up to ver...

Page 26: ...Vertiv Liebert PFD Installer User Guide 26 This page intentionally left blank...

Page 27: ...manufacturers specifications Opening or removing the covers to any equipment may expose personnel to lethal voltages within the unit even when it is apparently not operating and the input wiring is d...

Page 28: ...hose or with a commercial coil cleaner Check for bent or damaged coil fins and repair as necessary During winter do not permit snow to accumulate on or around the condensing unit Check all refrigerant...

Page 29: ...harge of high pressure refrigerant loss of refrigerant environmental pollution equipment damage injury or death This unit contains fluids and gases under high pressure Use extreme caution when chargin...

Page 30: ...Pull a second and third vacuum to 500 microns or less and verify that the vacuum levels are maintained 13 With the system in a 500 micron or lower vacuum charge the system based on the requirements l...

Page 31: ...out due to high discharge temperature condition Check display for high temperature alarm Set S303 to 0 or recycle power to indoor unit Controlvoltage fuses at transformer in evaporator module open Loc...

Page 32: ...ing pressures Refer to abnormalpressure causes if applicable Compressor motor protectors tripping or cycling High discharge pressure Check for blocked condenser fan or coil High suction temperature Ch...

Page 33: ...ert Thermal Management Products 1 800 543 2778 Liebert Channel Products 1 800 222 5877 Liebert AC and DC Power Products 1 800 543 2378 A 2 Locations United States Vertiv Headquarters 1050 Dearborn Dri...

Page 34: ...Vertiv Liebert PFD Installer User Guide 34 This page intentionally left blank...

Page 35: ...ions 3 4 and 5 ton horizontaldischarge DPN004066 Optionalanchoring plan 3 4 and 5 ton horizontaldischarge PFD Piping Schematics DPN004060 Piping arrangement 3 4 and 5 ton split system DPN004062 Piping...

Page 36: ...Vertiv Liebert PFD Installer User Guide 36 This page intentionally left blank...

Page 37: ...cess to refrigeration components electrical components and connections Top Air Discharge 2 51mm 3 76mm 4 3 4 121mm 23 9 16 599mm O 1 2 13mm Typical 6 places 2 1 8 53mm 35 15 16 913mm 5 TON HIGH AMBIEN...

Page 38: ...cess to refrigeration components electrical components and connections PRIMARY CONNECTION LOCATIONS 2 50mm 12 5 8 320mm 3 4 17 mm Liquid Line OD CU 1 1 8 29mm Suction Line OD CU MODEL NUMBERS 60Hz PFD...

Page 39: ...ressure Transducer External Equalizer Sensing Bulb Suction Line Digital Scroll Compressor Schrader Port with Valve Core Condenser Coil Discharge Temperature Thermistor 3 Way Head Pressure Control Valv...

Page 40: ...sor 3 Way Head Pressure Control Valve Check Valve Atmospheric Pressure Relief Valve Sight Glass Lee Temp Receiver Liquid Line Solenoid Valve Liquid Line Suction Line Receiver Heater Pressure Limiting...

Page 41: ...ET WEIGHT lbs kg DIMENSIONAL DATA in mm 30 3 4 781 48 1 4 1225 21 1 4 540 244 111 21 1 4 540 MODEL NUMBERS 18 5 8 473 18 5 8 473 B C 18 457mm min clearance required for proper air flow on both air inl...

Page 42: ...54A L PFD067A L ELECTRICAL CONNECTIONS in mm 7 8 1 2 MODEL NUMBERS 7 1 4 184 10 254 2 51 5 1 2 140 8 203 13 1 4 337 PIPING CONNECTION LOCATION in mm PIPING CONNECTION SIZES O D CU D C B A Removable Pa...

Page 43: ...3 15 11 16 398 15 3 8 391 2 5 16 58 7 1 8 181 6 3 8 162 F G H J K L M A B C D Coil Air 2 Typ 4 places 1 6 Receiver 1 PARTIAL FRONT VIEW 3 8 10mm Foot 3 8 10mm Field supplied spacer Typical 4 places No...

Page 44: ...ote 1 Disconnect Switch to be field supplied wired and mounted by others per local and national codes 2 Refer to specification sheet for full load amp and wire size amp ratings Electrical Entrance for...

Page 45: ...ect Switch to be field supplied wired and mounted by others per local and national codes 2 Refer to specification sheet for full load amp and wire size amp ratings Electrical Entrance for High Voltage...

Page 46: ...LOCATION DIAGRAM TYPICAL HORIZONTAL DISCHARGE CONDENSING UNIT LIEBERT PFD 1 2 3 4 5 1 Fan with Direct drive motor 2 Condenser coil 3 Electric box 4 Heated Receiver 5 Variable Capacity Digital Scroll...

Page 47: ...Vertiv Liebert PFD Installer User Guide...

Page 48: ...logos referred to are trade names trademarks or registered trademarks of their respective owners While every precaution has been taken to ensure accuracyand completeness herein Vertiv Co assumes no re...

Reviews: