Recommended sequence of operations
Operation instructions
cgm.
3
ENA type
IG-235-EN version 02
2
Recommended sequence of operations
2.1 Checking voltage presence and
phase balance
2.1.1
ekor.
spc
phase comparator
Ormazabal
offer the
ekor.
spc
unit for this purpose.
Firstly, connect the red cables of the
ekor.
spc
unit to the
corresponding phase test points on the voltage indication
units, and the black cable to the earth test point. This
operation should be repeated for all the phases: L1, L2 and
L3
Fig. 2.1:
ekor.
spc
unit
Fig. 2.2:
Connecting the
ekor.
spc
unit
Comparison of balanced phases
Fig. 2.3:
There is NO indication on the comparator
Comparison of unbalanced phases
Fig. 2.4:
YES, there is indication on the comparator
CAUTION
Before carrying out any operation when the
switchgear is energised, we recommend checking
the gas pressure, using the manometer.
In case of low gas pressure, contact to nearest
Ormazabal office.
Checking that the medium voltage cables are
correctly connected to the feeder switchgears must
be done. Comparison devices which comply with
the IEC 62271-206 standard may be used.
See section
1.1.1 Voltage presence indicator