1
Introduction
This manual describes setup and operating procedures for the Veeder-Root TLS2P Touch-Screen console. It assumes
that your system has already been set up by a Certified Contractor. This manual assumes that the console is installed
and has successfully completed the Cold Boot procedure. You should begin the setup procedure with the System
Setup Screens and finish with the Tank Setup Screens.
After entering the System and Tank Setup parameters the console should be operational. Consult the Reports Section
for instructions on viewing system and alarm reports. The Diagnostic Section contains some simple console test
procedures and access to Probe Diagnostic data.
Contractor Certification Requirements
Veeder-Root requires the following minimum training certifications for contractors who will install and setup the
equipment discussed in this manual:
Installer (Level 1) Certification:
Contractors holding valid Installer Certification are approved to perform wiring and
conduit routing; equipment mounting; probe, sensor and carbon canister vapor polisher installation; wireless
equipment installation; tank and line preparation; and line leak detector installation.
ATG Technician (Level 2/3 or 4) Certification:
Contractors holding valid ATG Technician Certifications are
approved to perform installation checkout, startup, programming and operations training, system tests,
troubleshooting and servicing for all Veeder-Root Series Tank Monitoring Systems, including Line Leak Detection.
Warranty Registrations
may only be submitted by selected Distributors.
Related Manuals
577013-959
TLS2P Ethernet, USB, 3 COMS Site Prep Manual
577013-767
RS-232 Serial Interface Manual for TLS2 UST Monitoring Systems