![Vapor Power RESISTO-FLO Instruction Manual Download Page 16](http://html1.mh-extra.com/html/vapor-power/resisto-flo/resisto-flo_instruction-manual_854232016.webp)
Page 16 of 18
Vapor Power International LLC
551 S County Line Road, Franklin Park, Il 60115
Phone: 630-694-5500 Fax: 630-694-2230
NOTE: TIGHTEN COMPRESSION FITTING TO 70 FT LBS Brass, 110 FT LBS SS MAX.
14.
Reverse the procedure outlined in steps 4-6 above using a new flange gasket.
15.
Refill boiler and purge air from system.
16.
Check for leaks both before and after system is pressurized.
DETAIL - ELEMENT INSTALLATION
FERRULE
#10-32 NUT
COPPER BUSS
#10-32 NUT
FLAT WASHER (#10)
CERAMIC
RUBBER
ELEMENT FLANGE
ELEMENT
(TIGHTEN: 70 FT LBS MAX BRASS
110 FT LBS MAX S.S.)
TIGHTEN ENOUGH
TO
BULGE RUBBER
SEAT (IN
FLANGE)
5.3.4
Probes
Level probes should be periodically checked. If there is any seepage between the
conductor and its insulator or between the insulator and the compression fitting,
replace the probe.
5.4
CLEANING THE BOILER
Boiler should be drained and cleaned periodically to remove any accumulated
scale or sludge. This can normally be done at the time of annual inspection unless
experience indicated that more frequent cleaning is required. Check for pitting of
vessel wall near water level and bottom head. Removal of the lowest element
flange usually facilitates this inspection.