0020244998_04 ecoTEC plus Installation and maintenance instructions
17
4
Boiler
5
Inspection hatch
A
Final storey
B
Ground floor
Note
The flue connecting from the appliance to the flue
system must be supplied from the manufacturer of
the boiler.
C43 flue systems must not be a 'pressurised sys-
tem' but act under natural draught principles.
C43 type flue systems must have their own con-
densate drain fitted and not allow condensate to
mix into other appliances.
The flue length must be calculated and installed according to
the relevant standards EN 13384-1 and 2 (C43 flue systems
only) with reference to the manufacturer's instructions sup-
plied. The appliance maximum flue length must be taken into
account when calculating the overall design of the flue sys-
tem.
Consult the separate installation manual for air/flue gas sys-
tems supplied with your appliance for all possibilities and as-
sociated accessories and how to install the flue system.
6.7
Using the installation template
▶
Use the installation template to ascertain the locations at
which you need to drill holes and make breakthroughs.
6.8
Wall-mounting the product
1.
Check whether the wall has sufficient load-bearing ca-
pacity to bear the operational weight of the product.
2.
Check if the supplied fixing material may be used for
the wall.
Condition
: The load-bearing capacity of the wall is sufficient, The fixing ma-
terial may be used for the wall
▶
Wall-mount the product as described.
1
2
3
▶
Install the reinforced product bracket
(1)
on the wall.
▶
Hang the shift-load cylinder on the product bracket from
above using the hanging bracket.
1
2
▶
Hang the heat generator
(2)
on the product bracket on
the shift-load cylinder
(1)
from above using the hanging
bracket.
Condition
: The fixing material may not be used for the wall
▶
Wall-mount the product as described using the permitted
fixing material provided on-site.
6.9
Removing/installing the front casing
6.9.1
Removing the front casing
B
A
B
▶
Remove the front casing as shown in the illustration.