Installation and maintenance instructions ecoTEC plus 0020031552_03
20
Use the template provided for the installation (see
Fig. 4.2).
The template shows the following:
the position of the fixing holes for the hanging bracket,
– the position of the connections.
– the position of the hole in the wall for the flue pipe.
• line the installation template up vertically and fix the
template to the wall.
• mark the position of the fixing holes for the hanging
bracket,
• drill 2 holes Ø 10 mm in the wall for the hanging bracket.
h
Note
Please take the total weight of the unit
combination and the load capacity of the wall
into account.
If necessary drill alternative fixing holes. If
necessary use alternative fixing materials.
4.5 Flue
exit
• If using rear flue mark the position of the air/flue duct
and its circumference.
• Remove the assembly template from the wall.
• If necessary cut the aperture in the wall for the flue pipe.
Other flue options
Instructions concerning other flue pipe systems, for
example, vertical flues, flue pipes to the side of the
boiler and the use of additional elbows etc. are listed in
the installation instructions for the flue pipe included
with the combi boiler.
4.6
Installation of the flue gas system
• Install the flue gas system (observe the separate
installation instructions for the flue pipe).
4.7
Fitting the appliance hanging bracket
1
3
2
Fig. 4.3 Shift load storage tank with hanging bracket
• Fix the hanging bracket (
1
) to the wall using the plugs
and screws (
2
) provided with the appliance.
• Lift the shift load storage tank out of the packaging
(see Section 3.4).
• Lift the shift load storage tank (
3
) onto the wall so
that it is located slightly above the hanging bracket (
1
).
• Slowly lower the shift load storage tank onto the
hanging bracket so that the installation carrier on the
rear of the unit fully engages in the hanging bracket.
h
Note
If the appliance is to be fitted in a timber
framed building ensure that the hanging brack-
et is secured to a substantial part of the timber
frame capable of taking the full weight of the
appliance.
4.8
Mounting the combination boiler
2
1
Fig. 4.4 Mounting the combi boiler on the shift load storage tank
• Lift the combi boiler out of the packaging (see Section
3.4).
• Lift the combi boiler (
2
) onto the shift load storage
tank so that it is located slightly above the shift load
storage tank (
1
).
h
Note
Lift the combi boiler at both sides of the base.
• Lower the combi boiler slowly onto the hanging brack-
et on the shift load storage tank so that the installation
carrier on the rear of the combi boiler fully engages in
the hanging bracket on the shift load storage tank.
4 Sequence of operations during installation
Summary of Contents for ecoTEC plus 937
Page 60: ......
Page 61: ......
Page 62: ......
Page 63: ......
Page 64: ...0020031552_03 GB 052008...