7 Handing the product over to the end user

14

Installation and maintenance instructions uniSTOR 0020235300_03

6.2

Cold water inlet pressure

The product's efficiency depends on the cold water inlet
pressure.

To achieve optimum efficiency, we recommend a pressure of
at least 2 bar.

6.3

Filling and purging the product

Note

It is not permitted to use valves or expansion relief
valves for the purging.

1.

Check whether the drain valve is closed.

2.

Check whether the inspection flap has been closed
correctly (800 l only).

3.

Open the domestic hot water draw-off valves.

4.

Open the water supply valve.

5.

Open the manual air separator at the top of the cylinder.

6.

Let the water flow in order to remove any air bubbles.

7.

Close the manual air separator as soon as all of the air
has escaped.

8.

Close the domestic hot water draw-off valves.

9.

Check whether there are any leaks. Check the immer-
sion heater in particular.

10. Open the highest hot water supply valve, and then the

lowest hot water supply valve, and let the water flow.

Water running time:

5 min

11. Close all of the draw-off valves.

7

Handing the product over to the end
user

Once the installation is complete, show the user the loca-
tion and function of the safety devices.

Inform the end user how to handle the product.

In particular, draw attention to the safety warnings which
the end user must follow.

Inform the end user of the necessity to have the product
maintained according to the specified intervals.

8

Troubleshooting

8.1

Detecting and eliminating faults

If problems occur whilst operating the product, check
certain points with the aid of the table in the appendix.
Detecting and eliminating faults (

Page 16)

8.2

Procuring spare parts

The original components of the product were also certified
by the manufacturer as part of the declaration of conformity.
If you use other, non-certified or unauthorised parts during
maintenance or repair work, this may void the conformity of
the product and it will therefore no longer comply with the
applicable standards.

We strongly recommend that you use original spare parts
from the manufacturer as this guarantees fault-free and safe
operation of the product. To receive information about the
available original spare parts, contact the contact address
provided on the back page of these instructions.

If you require spare parts for maintenance or repair
work, use only the spare parts that are permitted for the
product.

9

Inspection and maintenance

9.1

Observing inspection and maintenance
intervals

Adhere to the minimum inspection and maintenance inter-
vals. The inspection may require maintenance to be carried
out earlier, depending on the results.

Inspection and maintenance work

Overview (

Page 16)

The immersion heater can be removed in order to inspect
the inside of the cylinder.

9.2

Draining the product

1.

Close the cold water draw-off valve.

2.

Secure a hose to the drain valve.

3.

Position the hose at a suitable drain.

4.

Open the highest hot water tap in the installation.

5.

Open the drain valve and drain the product completely.

6.

Close the hot water tap and the drain valve.

7.

Remove the hose.

9.3

Checking the safety group's expansion
relief valve and the cylinder's expansion
relief valve

1.

Open all expansion relief valves by turning the plug.

2.

Check whether the water is flowing into the tundish.

3.

Check that the expansion relief valves are in the correct
position and then check the pressure.

4.

Check and, if required, clean the pressure reducer.

9.4

Checking the pre-charge pressure of the
expansion vessel

1.

Drain the product. (

Page 14)

2.

Measure the pre-charge pressure of the expansion ves-
sel at the vessel valve.

Condition

: Pressure <0.3 MPa (0.3 bar)

Top up the expansion vessel in accordance with the
static height of the heating installation, ideally with ni-
trogen, otherwise with air.

3.

If water escapes from the valve of the expansion ves-
sel, you must replace the expansion vessel.

4.

Fill and purge the product.

Summary of Contents for 0010019228

Page 1: ...maintenance instructions uniSTOR VIH RW GB 500 BES VIH RW GB 800 BES GB IE Publisher manufacturer Vaillant GmbH Berghauser Str 40 D 42859 Remscheid Tel 492191 18 0 Fax 492191 18 2810 info vaillant de...

Page 2: ...m clearances and installation clearances 8 5 Installation 8 5 1 Installing the product 8 5 2 Hydraulic connection 8 5 3 Electrical installation 11 6 Start up 13 6 1 Setting the immersion heater thermo...

Page 3: ...tenance instructions for the product and any other system com ponents installing and setting up the product in ac cordance with the product and system ap proval compliance with all inspection and main...

Page 4: ...rrect tool 1 4 5 Risk of material damage caused by frost Do not install the product in rooms prone to frost 1 4 6 Risk of injury due to the heavy weight of the product Make sure that the product is tr...

Page 5: ...egu lations The Benchmark Checklist can be used to demon strate compliance with Building Regulations and should be provided to the customer for future reference Installers are required to carry out in...

Page 6: ...llation area Select a sensible installation site and take into consideration the routing of the pipework system Install the cylinder as close as possible to the heat generator in order to minimise hea...

Page 7: ...ant ity Description 1 1 Expansion vessel 2 1 Tundish with retainer 3 1 Safety group 4 1 Documentation records 5 1 Domestic hot water cylinder Not included in the product s scope of delivery but is ava...

Page 8: ...correct method of draining is not followed In certain circumstances and at the dis cretion of the installer install a WRAS ap proved automatic air vent on the hot water outlet at the highest point ON...

Page 9: ...a tions that have a floor standing boiler AUTO MAIN OPEN 4 Install the 2 port motorised valve at the heating coil s inlet or outlet 5 For the 2 port motorised valve follow the installation direction t...

Page 10: ...must increase the diameter of the line When installing the drain line comply with the standards directives and laws that are applicable in your country Size of the outlet valve Minimum diameter of th...

Page 11: ...f water drains onto access paths 5 2 6 Installing the temperature sensor for the immersion heater Note The temperature sensor is used to control the im mersion heater via a connection box or a control...

Page 12: ...1 SPDT relay 2 Switch for immersion heater 3 SPUR fuse 4 Immersion heater 1 Remove the cover for the electrics on the cylinder 2 Install a separate power supply for the immersion heater in accordance...

Page 13: ...3 2 1 3 BLUE GREY GREEN ORANGE BROWN BROWN 1 Third party control 2 3 port motorised valve 2 port motorised valve 3 Heat generator Connect the assembly Condition Installation with a boiler 70 60 50 40...

Page 14: ...arts during maintenance or repair work this may void the conformity of the product and it will therefore no longer comply with the applicable standards We strongly recommend that you use original spar...

Page 15: ...ommissioning the product Switch off the heat generator Unplug the domestic hot water cylinder s mains plug Close the cold water stopcock Drain the product Page 14 Remove the hydraulic connections and...

Page 16: ...tat to 55 C 4 Replace the thermostat Irregular domestic hot water output at the valve 1 Defective expansion vessel 2 Thermal control 1 Set the expansion vessel 2 Interrupt the power supply of the prod...

Page 17: ...d pressure in the expan sion vessel 0 3 MPa 3 0 bar 0 3 MPa 3 0 bar Maximum temperature of the heating circuit 95 95 Maximum domestic hot water temperature 85 85 Heat loss 24 h energy effi ciency clas...

Page 18: ...sion heater to the power supply 230 V 50 Hz 230 V 50 Hz Immersion heater power 5 kW 7 5 kW Note Optional Low loss header 230 240 V 50Hz 230 240 V 50Hz Thermostat 230 240 V 50Hz 230 240 V 50Hz IP ratin...

Page 19: ...Appendix 0020235300_03 uniSTOR Installation and maintenance instructions 19 D Commissioning Checklist...

Page 20: ...UROV KDYH EHHQ WWHG LQ FRPSOLDQFH ZLWK 3DUW RI WKH XLOGLQJ 5HJXODWLRQV Yes Type of control system if applicable Y Plan S Plan Other Is the cylinder solar or other renewable compatible Yes No What is t...

Page 21: ...Date Engineer name Company name Telephone No Comments Signature SERVICE 05 Date Engineer name Company name Telephone No Comments Signature SERVICE 07 Date Engineer name Company name Telephone No Comme...

Page 22: ...10 Documents 5 Drain valve 9 Draining the product 14 E Electricity 3 F Filling and purging the product 14 Frost 4 H Handing over to the end user 14 I Identification plate 5 Inspection work 14 16 Insta...

Page 23: ......

Page 24: ...byshire DE56 1JT Telephone 0330 100 3461 info vaillant co uk www vaillant co uk These instructions or parts thereof are protected by copyright and may be reproduced or distributed only with the manufa...

Reviews: