UTS UTS 700 ONEMAN Instruction Manual Download Page 17

Page 17

 

UTS SALES & REPAIRS LTD

 

Dismantling

 

The dismantling procedure should follow the assembly steps in reverse order, take particular 
attention about the removal of guardrails and platforms.

 

You should ensure that you are standing in a safe position and always protected by guardrails 
NEVER remove diagonal braces or stabilisers prematurely.

 

After removing the toe

-

boards the operator disengages the horizontal guardrail brace clamps 

furthest from the trap door, horizontal guardrail braces are then removed with the operator 
positioned through the trap door before descending to the lower level, from where the upper 
platform and extensions/guardrail frames can be removed.

 

NOTES

:

 

DO NOT OVER

-

REACH and NEVER DROP COMPONENTS when dismantling always lower 

them to the ground.

 

STABILISERS

 

Attach one stabiliser to each corner of 
tower at approx. 45 degrees. The 
bottom clamp should be fitted as low 
as possible, refer to the diagram 
opposite. Ensure that all four rubber 
feet are in contact with the ground and 
that the clamps are secured. Position 
stabilisers as shown in the diagrams. 

 

When moving the tower lift each 
telescopic leg just clear of the ground, 
unlock castors ensuring the area is 
firm and clear of all obstructions both 
on the ground and above.

 

After moving check all castors are 
firmly on the ground and locked, and 
that the tower is vertical. Re

-

position 

stabilisers as above.

 

When using tower near a wall or in a 
corner, the stabiliser layout needs to 
adjusted to accommodate. 

 

As shown in the diagram if against a 
wall 2 stabilisers should be made 
parallel to the wall and the others 
should remain at 45°.

 

If being used in a corner, the closed 
corner stabiliser can be removed and 
the 2 near walls should be made 
parallel with the open corner stabiliser 
remaining at 45°.

 

STABILISERS—S3

 

 

Static Stabiliser maximum 

 

platform height of 4.2m

 

 

WALL

 

WAL

L

 

Summary of Contents for UTS 700 ONEMAN

Page 1: ...ssembly Personnel should be qualified or competent to erect this tower Please consult the PASMA s code of practice for full information on the use of Mobile Access Towers Remember to do a risk assessm...

Page 2: ...UTS 700 ONEMAN INSTRUCTION MANUAL Page 2...

Page 3: ...nce 6 Components and Weights 8 Assembly 9 Dismantling 17 Configurations and Weights 18 Risk Assessment Form 19 UTS 700 ONEMAN Instruction Manual Mobile Access Tower UTS SALES REPAIRS LTD UNIT 1A CANTE...

Page 4: ...efore assembly or erection of this Mobile Access Tower MAT please ensure that A risk assessment has been done and all safety equipment is on site The ground conditions will take the working loads of M...

Page 5: ...and only from the base Beware of overhead obstructions live wires hanging apparatus or other objects Do not move with people or material on the tower Do not move the assembled MAT if wind speeds exce...

Page 6: ...ded as a complete structure Always keep this instruction manual safe Broken damaged or incorrect components must never be used The equipment shall be quarantined and assessed for replacement repair or...

Page 7: ...braces DOWNWARD or from the inside facing OUTWARD BUT NEVER INWARD FITTING ADJUSTABLE LEGS Take the adjustable leg assembly complete with its castors make sure that all the adjusting nuts are positio...

Page 8: ...em Description Weight Kg 1 150mm Locking Caster 3 4 6 1 3m OMT Brace 6 2 Adjustable Leg 500mm 1 1 7 Complete Toe Board Set 6 3 1m 4 Rung Frame 5 6 8 OMT Hanging Bracket 1 4 1 3m Trapdoor Platform 9 1...

Page 9: ...e never the outside When working on the platform never overreach The end frames should provide a firm hand hold Insert adjustable leg assembly with castors or base plates into the base of a rung end f...

Page 10: ...sure bottom clamps are locked refer to page 7 Insert 4 rung sides onto each end of the tower ensure they clip in refer to page 6 Fit OMT Brace to 6th and 8th rungs of towers ensure bottom clamps are l...

Page 11: ...S SALES REPAIRS LTD Fit a trap door platform to 4th rung of the tower engage the wind locks If completing at 1 2m fit toe boards to the working platform see instructions on page 4 5 If not continue to...

Page 12: ...ng frames together using the clips then climb the tower on the inside using the rungs of the end frames Fit these double 4 rung ends to each end of the tower as shown Fit a OMT Brace to the 9th and 11...

Page 13: ...2th rung lock wind locks From a seated position within the trap door of the platform fit a OMT Braces to the 14th and 16th rungs of the tower then ensure the bottom clamps are locked Fit toe boards to...

Page 14: ...er using the clips then climb the tower on the inside using the rungs of the end frames Insert these onto each end of the tower ensure they clip in refer to page 6 Fit a OMT Brace to the 5th and 7th r...

Page 15: ...d From a seated position within the trap door of the platform fit a OMT Braces to the 14th and 16th rungs of the tower then ensure the bottom clamps are locked If completing at 2 2m fit toe boards to...

Page 16: ...hown Add a platform on the 16th rung lock wind locks Fit a OMT Brace to the 13th and 15th rungs of the tower the hang an assembly bracket from it to all the easy moving of components to higher levels...

Page 17: ...tower at approx 45 degrees The bottom clamp should be fitted as low as possible refer to the diagram opposite Ensure that all four rubber feet are in contact with the ground and that the clamps are s...

Page 18: ...g 500mm 4 4 4 4 1m 4 Rung Frame 4 6 8 10 1 3m Trapdoor Platform 1 1 2 1 3m Horizontal Brace 1 1 1 3m OMT Brace 3 4 Complete Toe Board Set 1 1 OMT Assembly Tool 0 1 Instruction Manual 1 1 S3 Stabiliser...