Installation Manual 201.1

 

SolarMount

®

 Top Mounting

Installing the modules

Prewiring Modules.

 If modules are the Plug and Play type, no prewiring is 

required, and you can proceed directly to “Installing the First Module” below.  

If modules have standard J-boxes, each module should be prewired with one 
end of the intermodule cable for ease of installation. For safety reasons, module 
prewiring should not be per formed on the roof.

Leave covers off J-boxes. They will be installed when the modules are installed 
on the rails.

Installing the First Module.

 In high-profi le installations, the safety bolt and 

fl ange nut must be fastened to the module bolt slot at the aligned (lower) end of 
each rail. It will prevent the lower end clamps and clamping bolts from sliding 
out of the rail slot during installation.

If there is a return cable to the inverter, connect it to the fi rst module. Close the 
J-box cover. Secure the fi rst module with T-bolts and end clamps at the aligned 
end of each rail. Allow half an inch between the rail ends and the end clamps 
(Fig. 15). Finger tighten fl ange nuts, center and align the module as needed, and 
securely tighten the fl ange nuts (15 ft lbs).

Installing the Other Modules.

 Lay the second module face down (glass to 

glass) on the fi rst module. Connect intermodule cable to the second module and 
close the J-box cover. Turn the second module face up (Fig. 16). With T-bolts, 
mid clamps, and fl ange nuts, secure the adjacent sides of the fi rst and second 
modules. Align the second module and securely tighten the fl ange nuts (Fig. 17).

For a neat installation, fasten cable clamps to rails with self-tapping screws.  

Repeat the procedure until all modules are installed. Attach the outside edge of 
the last module to the rail with end clamps.

Trim off any excess rail, being careful not to cut into the roof. Allow half an inch  
between the end clamp and the end of the rail (Fig. 15).

Check that all fl ange nuts on T-bolts are securely fastened.

Figure 18. Size G clamps (for modules with high lips) 
include a spacer for the end clamps but are otherwise 
identical. Size H mid clamps and end clamps (for mod-

Figure 15

Figure 16

Figure 17

High-lipped module

(cross section)

SolarMount rail with Size H clamps

Low-lipped module

(cross section)

SolarMount rail with G clamps and spacer

Spacer

ules with low lips) are identical and employ hexhead 
bolts in place of T-bolts; their heads slide into Solar-
Mount

®

 rails.

1

/

2

" minimum

1

/

4

" module bolt

and 

fl

 ange nut

Rail

End clamp

Module 

frame

J-boxes

Module frames

1

/

4

" module bolt

and 

fl

 ange nut

Mid clamp

Summary of Contents for SolarMount

Page 1: ...ng 3 8 flange Rail length inches rails L feet bolts nuts 48 106 2 4 4 4 120 180 2 6 6 6 192 216 2 8 8 8 226 288 w splice 2 10 10 10 300 336 w splice 2 12 12 12 348 408 w splice 2 14 14 14 420 432 w splice 2 16 16 16 Top Mounting Clamp Sets Sizes A F G H and J Modules End Mid module x 5 8 flange per row clamps clamps T bolts safety bolts nuts 2 4 2 6 2 8 3 4 4 8 2 10 4 4 6 10 2 12 5 4 8 12 2 14 6 4 1...

Page 2: ...or replacement shall completely satisfy and discharge all of UniRac s liability with respect to this limited Warranty Under no circumstances shall UniRac be liable for special indirect or consequential damages arising out of or related to use by Purchaser of the Product Manufacturers of related items such as PV modules and flashings may provide written warranties of their own UniRac s limited Warra...

Page 3: ...t rail sets Apply sealant into the hole and on the shafts of the lag bolts Seal the underside of the L feet with a suitable weatherproof sealant Securely fasten the L feet to the roof with the lag bolts Ensure that the L feet face as shown in Figure 6 or Figure 7 The single slotted square side of the L foot must always lie against the roof with the double slotted side perpendicular to the roof Fig...

Page 4: ...bove the rafters Adjust as needed following the guidelines in Figure 10 as closely as possible Installing standoffs Drill 3 16 inch pilot holes through the underlayment into the center of the rafters at each standoff location Securely fas ten each standoff to the rafters with the two 5 16 x 31 2 lag bolts provided with it Verify that the lag bolts you use are adequate for your installa tion by fol...

Page 5: ...tach the rails to the footings with the flange nuts Ensure that the rails are oriented to the footings as shown in Figure 6 7 9 or 10 whichever is appropriate Aligning the Rail Ends Align one pair of rail ends to the edge of the instal lation area Fig 13 or Fig 14 The opposite pair of rail ends will overhang the side of the installation area Do not trim them off until the installation is complete I...

Page 6: ...odule as needed and securely tighten the flange nuts 15 ft lbs Installing the Other Modules Lay the second module face down glass to glass on the first module Connect intermodule cable to the second module and close the J box cover Turn the second module face up Fig 16 With T bolts mid clamps and flange nuts secure the adjacent sides of the first and second modules Align the second module and securely...