background image

Series 4000 Side-of-Pole PV Module Rack

(Formerly U-05)

Installation Sheet 406.2

© 2004 by UniRac, Inc. 

All rights reserved.

Pub 040623-3ii

June 2004 

UniRac welcomes corrections, clarifi cations, or other input concerning 

this manual. Please write to 

[email protected].

Thank you for purchasing a UniRac. Please review this manual completely 
before proceeding.

The installer is solely re spon si ble for:

•  Complying with all applicable local or national building codes, 

including any that may supercede this manual;

•  Ensuring that UniRac and other products are appropriate for the 

particular installations and are designed for the installation envi-
ronment;

•  Using only UniRac parts and installer-supplied parts as specifi ed by 

UniRac (substitution of parts will void the warranty);

•  Ensuring safe installation of all electrical aspects of the PV array.

Parts List

Part                           Qty.

Channel                      1
Bracket, left-hand         1
Bracket, right-hand       1
Rail                             2

Mounting pole guidelines

The installer is solely responsible for use of the in for ma tion 
below. These are general guide lines for normal in stal la tions. 
The following variances can affect your installation:

•  The required diameter and depth of the hole are 

dependent on soil type, which varies by locale. An 
in stal la tion in loose, sandy soil will require larger, 
deeper holes and, there fore, more concrete than an 
in stal la tion in soil of average density.

•  The depth and width of the hole should also be in-

creased in areas subject to winds in excess of 90 mph, 
particularly if the location of the mount ing pole is 
open and unprotected.

•  Poles taller than 6 feet above ground require that the 

depth of the hole be increased.

If in doubt, consult a professional civil engineer who is familiar 
with local soil conditions and wind load re quire ments.

1.   Dig a hole 8 to 12 inches in diameter and 36 to 40 

inches deep. Fill the bottom with 4 inches of gravel.

2.   Stand the pipe in the hole. Brace the pole so that it 

is plumb. Pour con crete around the pipe, fi lling the 
hole to ground level.  Add an inch or two of extra 
concrete above the hole. Use a trowel to slope the 
concrete around the pole.

3.    Allow the concrete to set up for at least 24 hours 

before installing your UniRac.

                                          Wrench     Recommended
Part                            Qty.        size         torque (ft-lbs)

Hex-head bolt, 

¼˝

       4         

7

/

16

˝

               15

Hex-head bolt, 

5

/

16

˝

     8           

½˝

               20

U-bolt, 

3

/

8

˝

                  1

Flange nut, 

¼˝

             4         

7

/

16

˝

               15

Flange nut, 

5

/

16

˝

           8           

½˝

               20

Flange nut, 

3

/

8

˝

            2         

9

/

16

˝

               30

Before assembly

This rack is intended for side mounting on a 2-inch Schedule 40 or Schedule 
80 steel pole (2 

3

/

8

˝

 O.D.), which is not included with the rack. UniRac supplies 

hardware that fi ts a 2-inch pole. U-bolts for poles up to 4 inches are available at 
extra cost.

Use the Parts List to verify that all parts are present.

If desired, excess rail length can be cut off. Cut between rail slots—never 
through a slot.

Caution

Stainless steel hardware can seize up, a process 
called galling. To sig nifi   cant ly reduce the like li hood 
of galling, apply a small drop of anti-seize lubricant 
to the threads of all  bolts before installation.  
Anti-seize lubricants are readily available in auto 
parts and hardware stores. In their absence, any 
lubricant will reduce chances of galling.

Reviews: