Testing the wire rope hoist

10 Testing the wire rope hoist

The electric wire rope hoist can be used after: UVV  
"Winches, lifting and pulling equipment" BGV D8 (VBG 
8), UVV "Cranes"  BGV D6 (VBG 9). 

Testing in compliance with BGV D8 Section 23 (VBG 8 
Section 23) by a specialist before commissioning and 
following major changes. 

Testing in compliance with BGV D6 Section 25 (VBG 9 
Section 25) by an authorised expert before commission-
ing and following any major changes. 

Annual repeat testing of equipment, crane and support-
ing structures by a specialist. Where equipment is sub-
ject to heavy operational conditions (e.g. frequent oper-
ation with a full load, dusty or aggressive environment, 
frequent stopping, long operation time) the testing inter-
vals should be reduced.

- With regard to testing cranes, experts are exclu-

sively TÜV experts or experts authorised by pro-
fessional bodies or associations.

- Specialists are customer service installers em-

ployed by the manufacturer or specially trained 
specialist personnel.

Evidence of wire rope hoist testing should be kept in an 
inspection log book.

Testing is generally a visual and functional test. It in-
cludes an inspection of the condition of the components 
and equipment, the completeness and functionality of 

the safety equipment and the completeness of the log 
book. 

11 Disposal, recycling of used devices

Please take care in your own interest and in the interest 
of the environment that all component parts of the ma-
chine are only disposed of in the intended and permit-
ted way. 

11.1 Decommissioning

Immediately decommission disused machines in order 
to avoid later misuse and endangering of the environ-
ment or personal safety.

Step 1: Eliminate all environmentally hazardous operat-

ing materials from the used device.

Step 2: If required, disassemble the machine into easy-

to-handle and usable components and parts.

Step 3: Dispose of machine components and operating 

materials by the disposal channels provided.

11.2 Disposal of lubricants

Remove any leaking, used or excessive grease at the lu-
bricating points. 

Disposal notes for used lubricants are available from the 
manufacturer of the lubricants. If necessary, request the 
product-specific data sheets.

12 Fault finding

Failures

Possible cause

Solution

wire rope hoist motor is not function-
ing.

1. Switch defective.
2. Motor defective.
3. Bad contact.

1. Replace switch.
2. Change motor.
3. Check contacts.

Temperature of motor too high.

Long service life.

 File cooling phases.

Motor operates, wire rope hoist does 
not operate.

1. Coupling is not engaged.

When the problem occurs further-

more, inform the service. 

wire rope hoist operates with too low 
power or too low speed. 

1. Battery power is too low.
2. Bad contact.
3. Insufficient recharge.

1. Load or replace battery.
2. Check connections. 
3. Check charger and replace if nec-

essary.

Motor is wet.

Humidity is too high or water ingress.

Drain the water. Dry the device. After 
that start the motor and let it operate 
for a little while. Repeat this proce-
dure a few times. 

Summary of Contents for ESW 900

Page 1: ...ESW 900 ESW 900 Operating Instructions Electric Wire Rope Hoist ESW 900...

Page 2: ...Customer service 3 1 3 Limitation of liability 3 2 Safety 3 2 1 Symbol explanation 3 2 2 Obligations of the operating company 4 2 3 Requirements to staff 5 2 4 Personal protective equipment 5 2 5 Gene...

Page 3: ...e to develop our products even further 1 3 Limitation of liability All information and notes in these operating instructions were summarised while taking applicable standards and rules the state of th...

Page 4: ...repared by her correspond to the current status of the regulations and must adapt these if necessary The operating company must unambiguously reg ulate and determine the responsibilities for instal la...

Page 5: ...the manufacturer Other personnel is not au thorized to perform these works Please contact our cus tomer service for the execution of all arising work 2 4 Personal protective equipment The personal pro...

Page 6: ...e requiring inspection For this reason the following guidelines issued by the trade association central office for accident prevention regarding steel cables used in lifting operations must be complie...

Page 7: ...arrier or dealer 5 2 Packaging All used packaging materials and packaging aids are recyclable and should be taken to a materials recycling depot to be disposed of The delivery packaging is made of car...

Page 8: ...e bottom onto an appropriate beam Step 3 Oil the cable before you use it for the first time Step 4 Connect the battery connection cable and the control panel with the connections of the wire rope hois...

Page 9: ...l and the load may drop The wire rope hoist load hook should only be secured to suitable suspension points on the load Under no circumstances may a load be subjected to a heavy blow or collision ATTEN...

Page 10: ...d undam aged condition Step 2 Check that the voltage of the voltage source is a 12 V direct current Step 3 Connect the crocodile clips to a 12 V battery The red cable with the positive pole and the bl...

Page 11: ...rdance with the actual signs of wear Contact the manufacturer for further information concerning mainte nance tasks and intervals Please find the contact data on chapter 1 2 Customer service Step 1 Lu...

Page 12: ...ge The cable guide should be checked when changing the cable and replaced if necessary Fig 5 Steel cable Maintenance intervals Maintenance tasks before each operation Check wire rope hoist for damage...

Page 13: ...he hook part 1 Fig 7 Dimension of the hook part 2 Fig 8 Dimension of the hook part 3 Fig 9 Dimension of the hook part 4 According to DIN 15405 Part 1 the load hook should be replaced if it has widened...

Page 14: ...and in the interest of the environment that all component parts of the ma chine are only disposed of in the intended and permit ted way 11 1 Decommissioning Immediately decommission disused machines i...

Page 15: ...re on the type plate fixed to the electric wire rope hoist Example Load hooks for the electric wire rope hoist must be or dered Type of device Electric wire rope hoist ESW 900 Item number 6190900 Posi...

Page 16: ...2 Spare parts drawing In case of service the following drawing shall help to identify the necessary spare parts If necessary send a copy of the parts drawing with the marked components to your author...

Page 17: ...Spare parts ESW 900 Version 2 04 17 13 3 Electrical wiring diagram ESW 900 Fig 11 wiring diagram ESW 900...

Page 18: ..._____ complies with all relevant provisions of the above mentioned directive as well as the other applied directives below including their applicable modifications at the time of the declaration EU di...

Page 19: ...0 h As nec essary As nec essary As nec essary annu ally Function test coupling cleaning as necessary wear test coupling Measurement of wear Cable hook Replacement switch connection cable Replacement c...

Page 20: ...www unicraft de...