3.

 

CONNECTION BETWEEN A ZHERO AND THE PHOTOVOLTAIC GENERATOR

 

 

 

 

INSTALLATION

 

 

 

Figure 1 - MPPT inlet hatch

 

  The installation consists in connecting the cables coming from 

the photovoltaic system to the pre-assembled MC4 of the 

charge controllers, paying close attention not to reverse the 

polarity.  

 

To do this, remove the plate (Figure 1) by unscrewing the 

appropriate screws of the plate. Once the plate has been 

reinstalled and the cables brought inside the system, they can be 

connected to the regulators via the MC4 photovoltaic connector.  

 

According to the type of regulator installed, check that the 

string voltage is between 90 - 150 V or 200 - 600 V.  

 

ATTENTION

: It is necessary to install a PV unloader (SPD), 

external to the machine, with Up index

 Up ≤ 2.5 kV

 

 

 

 

 

   

4.

 

AC CONNECTION - A ZHERO TO MAINS DISTRIBUTOR/GENERATOR and "BACKUP" 

 

 

Figure 2 - ZHERO terminal block connection

 

 

INSTALLATION

 

 

 

Connection  of  the  distributor  /  genset  network  entering  the 

system (not production meter):  

 

LG

: 230VAC DISTRIBUTOR / GENERATOR phase  

 

NG

: Neutral DISTRIBUTOR / GENERATOR 230VAC  

 

Yellow / Green terminal

: earth connection 

 

Connection of the "backup" line (optional):  

 

LC

: 230VAC Backup Phase  

 

NC

: Neutral Backup 230VAC  

 

Yellow / Green terminal

: earth connection  

 

Connection of the production meter:  

 

LO

: input phase to the production counter on the inverter side  

 

NO

: neutral on inverter side counter input  

 

LOO

: Output phase from the grid side production meter 

 

NOO:

 Neutral in output from the grid side production meter  

 

In  case  of  Off-grid  application,  a  jumper  must simply  be made 

between LOO and LO and between NOO and NO.  

Summary of Contents for ZHERO

Page 1: ...ZHERO QUICK INSTALLATION GUIDE Single phase series 3 0 UNE srl Via Modena 48 E 42015 Correggio RE Italia Tel 39 0522 693566 info unesrl com https unesrl com...

Page 2: ...st be delivered signed to the customer at the end of all the procedures described 1 PLACEMENT OF A ZHERO In flat floor in easily accessible places in a position to ensure access to the switches in a p...

Page 3: ...0 V or 200 600 V ATTENTION It is necessary to install a PV unloader SPD external to the machine with Up index Up 2 5 kV 4 AC CONNECTION A ZHERO TO MAINS DISTRIBUTOR GENERATOR and BACKUP Figure 2 ZHERO...

Page 4: ...ct the output utilities from the wattmeter then downstream of the corresponding terminals 2 and N Figure 4 Wattmeter communication connection diagram 485 Wattmeter ZHERO communication connection Conne...

Page 5: ...LG NG terminals has been disconnected for at least 30 seconds Move the BYPASS switch to position 1 Up to put the loads of the LC NC line under the backup line if the backup line is provided Enable the...

Page 6: ...AD AREA The reading of the bits through UneSrlCommunication must be carried out from the bottom right to the left upwards DETAIL STATUSCYCLE ALARMS VERIFY Figure 7 Detail of machine states STATUSCYCLE...

Page 7: ...alarm is all 0 DETAIL ALARM MPPT VERIFY Figura 10 Controller alarm details To check the communication of the controllers select the CONT0 CONT1 and CONT2 boxes depending on whether you have 1 2 or 3 c...

Page 8: ...from the website https unesrl com in the section DOWNLOAD AREA Internet connection if the system is not online for more than 48 consecutive hours before opening a technical assistance ticket it is ne...

Reviews: