PERGOLA INSTALLATION
Fit outer bars first and then remaining bars. Locate over bolts (Q8077,
split) and secure using the M5 nuts (Q8400/2) provided.
From roll of glazing tape (AVA003) provided, cut lengths to fit between
glazing bars along curved beam.
7
9
Lift 6mm or 10mm toughened pieces of safety glass into place. Centralise
glazing between bars and place against supports at bottom of bars.
Fit glazing beads to each bar securing glazing. Push bead up against
wallplate. Engage lower leg into groove and work from one end to the
other using thumb pressure to compress the gasket and engage the top
clip of the bead. Constant pressure needs to be applied along the bead
as you work along so it will require 2 people.
NOTE: If beading becomes
difficult, it is advisable to use warm soapy water on the bead gasket.
11
10
Repeat at bottom of bars, locating over bolts (Q8077, split) and securing
using the M5 nuts (Q8400/2) provided. Ensure that structure is square
and at correct pitch (adjust props to suit) and fix into Veranda beam
using screws (CHA008) provided.
8
On the outer bars, secure cloaking trim using the 3 screws (CHA007)
and caps (Q8084, Q8685) provided (outer legs of glazing end stop
bracket should have been cut back to allow trim to fit).