Tuthill KINNEY SDV SDV-120 Installation Operation Maintenance Repair Manual Download Page 11

11

• 

Flow rates listed are Minimum.

• 

FLUSHING PURGE should last for 30 minutes with the pump suction valve closed, after process operation is ended.

• 

All PURGE work except for flushing should be done at the same time as the process starts up.

• 

Sealing purge at NON-DRIVE END can vary a little according to the type of process and operating condition.

• 

The COOLING PURGE amount can vary with the vacuum level. 

HANDLING PROCEDURE

ASSEMBLY OF PIPING

LOCATION

1.  The pump should be mounted on a base frame with sufficient rigidity and placed on a flat and level surface.  
2.  If it is to be installed outdoors, please ensure the motor, painting, peripheral equipment, and parts, etc. are suitable for the 

outdoor operations.

3.  There should be enough space around the pump to allow for safe maintenance work and periodic inspections.

FOUNDATION

1.  Foundation for the pump assembly and it’s base frame should be flat, leveled, and have adequate load bearing capacity.  
2.  Pump and its base frame, peripheral equipment and piping should be installed when the fountation concrete has been cured.  

INSTALLATION

1.  SDV pumps should always be operated in a horizontal and level position.  SDV pumps should never be installed in an upright 

(vertical) or angled position, and should be installed on a rigid base frame.

2.  Pump assembly with the base frame should be placed on a foundation and should be supported evenly.  Metal shims should 

be inserted between the base frame and the foundation, if required for leveling.  Pump assembly with the base frame should be 

leveled to within 0.5 mm (0.02”) in any 1 meter (3.28 ft)

3.  Use adequately sized anchorbolts.
4.  Upon completion of the setting of the pump assembly on the foundation and anchorbolts, the base frame should be adequately 

grouted prior to tightening the anchorbolt nuts.  Anchorbolt nuts should be tigtened after the grout is firmly cured.  Anchorbolts 

should be tightened evenly to ensure the previously set level is not changed.

PIPING WORK

MAIN PIPING

1.  Process Piping internals should be clean and free from rust, dust, foreign materials, weld slag’s etc. 

   

2.  A 40-mesh strainer supplied along with the SDV pump should be placed at the pump process inlet nozzle.  After initial start-up 

and continued operation of the SDV pump for several hours, disassemble the process inlet piping from the pump and check 

the strainer for cleanliness.  If there are any particulates strained such as weld slags etc, clean the mesh strainer and replace to 

the pump process inlet nozzle.  It is highly recommended to check this strainer regularly for its integrity and cleanness.  

3.  It is required to install expansion joints on the suction side of the pump as well as the discharge side of the pump.  These 

expansion joints are to prevent direct application of any excessive load (primary and secondary load) to the pump assembly 

from the process piping structures.  Process piping must be supported and guided such that the pump assembly is relatively 

free from any excessive load imposed from the process piping structures.   

4.  Where process exhaust silencer is provided, it should be installed on or as near to the pump discharge nozzle as possible.  
5.  A check valve should be installed as close to the process inlet nozzle as possible, which is used to isolate the pump from the 

process during the pump shut down.  The pump will turn in reverse direction if check valve is not present at the process inlet 

nozzle by the pressure differentials.  Where a check valve installation is not permitted for any reason, a process isolation valve, 

such as a gate valve, should be installed.  However, operational procedures must include a pump shut down procedure that 

includes closure of this process isolation valve prior to pump shut down.  It is highly recommended to install a process inlet 

isolation valve whether a process inlet check valve is installed or not.  

6.  Where the process gas contains high condensable vapors, a condensate recovery tank should be installed.  The tank should 

be designed to collect the condensates and disposed or drained, as it required.

COOLING WATER PIPING — SDV pumps are equipped with an integrated cooling liquid jackets.  A cooling medium, typically 

water, must be supplied to the cooling liquid supply nozzle located at the FEC (Front End Plate) which will be circulated to the pump 

Casing and discharged from the discharge nozzle located on the Casing.  Where water-jacketed discharge silencer or after cooler 

is supplied with the pump, the silencer or after cooler should also receive the cooling liquid as well.  A single loop cooling liquid 

Summary of Contents for KINNEY SDV SDV-120

Page 1: ...ATION OPERATION MAINTENANCE REPAIR MANUAL WARNING DO NOT OPERATE BEFORE READING MANUAL Tuthill Vacuum Blower Systems 4840 West Kearney Street Springfield Missouri USA 65803 8702 o 417 865 8715 800 825 6937 f 417 865 2950 www tuthillvacuumblower com 1861 Rev A 0912 ORIGINAL LANGUAGE ENGLISH ...

Page 2: ...ly unfriendly chemical vapor pump discharge must be connected to the properly sized scrubber system to neutralize the harmful chemicals prior to the discharge to the atmosphere Laws and ordinances may pertain to your local area regarding discharge of oil mist oil vapor chemical vapor to atmosphere Check local laws and ordinances prior to operation of the pump with discharge to outside atmosphere D...

Page 3: ... METHOD AFTER PUMP OPERATION 10 HANDLING PROCEDURE 11 ASSEMBLY OF PIPING 11 PIPING WORK 11 OPERATION 12 PREPARATION FOR OPERATION 12 OPERATION 12 PUMP SHUTDOWN 13 LUBRICATION 13 MAINTENANCE AND INSPECTION 13 GENERAL 13 PERIODIC INSPECTION SCHEDULE 13 DRY VACUUM PUMP MAINTENANCE INSPECTION SCHEDULE 14 DISASSEMBLY AND REASSEMBLY 15 16 DISASSEMBLY PROCEDURE 15 REASSEMBLY PROCEDURE 16 VACUUM SYSTEM CH...

Page 4: ...AL OF OPERATION The SDV Dry Screw Vacuum Pump is a single stage dry running non contact variable pitch screw type vacuum pump The design principle of the SDV is simple Two parallel variable pitch screws having a highly sophisticated surface profile consisting of an Archimedean and Quimby curve and an arc rotate in opposite directions Drive shaft rotation is CW when viewed from the motor end drive ...

Page 5: ...ming gears and lubricates the Bearings and Mechanical Seals OIL LEVEL SENSOR An oil level sensor is an optional item and may be installed inside the front end cover to sense low oil level and protect the mechanical seals and bearings In case of improper or low oil lubrication the oil level switch will send a signal or alarm to alert an operator to refill the oil to the proper level MATERIALS OF CO...

Page 6: ...122 50 122 50 122 50 122 50 122 50 122 50 Discharge Gas F C 392 200 392 200 482 250 482 250 572 300 572 300 572 300 Oil F C 158 70 158 70 158 70 158 70 158 70 158 70 158 70 Grease F C 176 80 176 80 176 80 176 80 176 80 176 80 176 80 Noise dBA 4 72 72 80 80 85 85 90 Weight lbs kg 396 180 484 220 616 280 770 350 1212 550 2310 1050 2970 1350 Dimmensions L x W x H 5 Inches mm 19 13 1 10 3 483 332 262 ...

Page 7: ...oling water discharge temperature For SDV 200 and larger sized pumps the cooling water circuit is extended to the process exhaust silencer For SDV 120 silencer is not jacketed hence cooling water circuit is not extended to the process exhaust silencer Figure 1 Typical Process and Inlet Discharge for SDV 120 with Once Through Cooling S FI MOTOR SILENCER PROCESS INLET VG PI FSL TI COOLING WATER SUPP...

Page 8: ...d pumps the cooling water circuit is extended to the process exhaust silencer For SDV 120 silencer is not jacketed hence cooling water circuit is not extended to the process exhaust silencer Figure 3 Typical Process and Inlet Discharge for SDV 120 with fan cooled re circulated cooling water system Figure 4 Typical Process and Inlet Discharge for all other SDV models with fan cooled re circulated c...

Page 9: ...ted to two purge connection nozzles on the Front End Cover Non Drive End NDE Seal Purge should be connected to two purge connection nozzles on the Rear End Plate REP For SDV 120 there s only one Non Drive End NDE Seal Purge connection nozzle Both Drive End DE and Non Drive End NDE Seal Purges can be manifolded from a single source of purge gas supply Seal Purge pressure should be below 0 5 kg cm2g...

Page 10: ...t have a high potential for build up and are aggressive in nature such as processes with Oligomer Monomer Polymer Resin etc should be cleaned out regularly by Steam Flushing 1 Steam pressure Approximately 1 kg cm2g 14 22 psig 2 System Isolation Disconnect all electrical and control powers and place lockout tags on the MCC and or Control Panel to ensure no one accidentally starts the pump during th...

Page 11: ...le After initial start up and continued operation of the SDV pump for several hours disassemble the process inlet piping from the pump and check the strainer for cleanliness If there are any particulates strained such as weld slags etc clean the mesh strainer and replace to the pump process inlet nozzle It is highly recommended to check this strainer regularly for its integrity and cleanness 3 It ...

Page 12: ...arts within the DE Drive End Casing OPERATION 1 Ensure the direction of the pump rotation is correct CW Clockwise direction looking from the motor A pump rotational direction check can be done by jogging the pump a brief moment while checking the rotational direction of the motor fan If the motor rotates CCW Counter Clockwise correct the power cable connections and check the rotational direction a...

Page 13: ... some cases the screws and the casing may have become corroded This corrosion will cause the clearance between the screws and casings to increase and increase the slip internal reverse flow flow of gas from the pump discharge to the suction The pumping capacity of the pump is then decreased In this case the pump must be shutdown and clearances must be measured and verified in order to determine re...

Page 14: ...ction correct Suction Discharge Pressure Is the pressure as specified Noise Vibration Any abnormal sound or vibration Temperatures Any excessive oil or water temperature Cooling Liquid Leak Check for leakage of the cooling liquid Oil Level Gauge Is oil at proper level Water contamination on free end cover What is the color Has it changed to reddish brown Cooling Water Pressure Is the pressure as s...

Page 15: ...ide NDS Non Drive Side DE Drive End NDE Non Drive End FEC Front End Cover FEP Front End Plate REP Rear End Plate DISASSEMBLY PROCEDURE FEC DISASSEMBLY 1 Disconnect all process and utility piping and electrical controls connections 2 Remove motor coupling key 3 Drain oil and cooling liquid from the pump 4 Relocate the pump to a safe workbench suitable for disassembly reassembly work Workbench shoul...

Page 16: ...In position 4 Insert Lantern Rings with O rings O ring side UP Ensure the O rings are in place within the O ring glands 5 Check the Mechanical Seal Stator A O rings materials of construction Where the application requires special O rings such as Kalrez O rings ensure the O rings on Mechanical Stator A are meet the requirements If required replace the Mechanical Seal Stator A O rings with correct O...

Page 17: ...ace NDS Timing Gear key and NDS Timing Gear onto the Driven Shaft 39 Replace Lockwashers and Locknuts Bend one edge the Lockwasher to fix its location 40 Replace DS Timing Gear onto the Drive Shaft 41 Install Power Lock on the DS Timing Gear 42 Insert feeler gauge into the Screw clearance inside of the process inlet nozzle as shown on the Figure 4 43 Per the Screw Clearance Table set the clearance...

Page 18: ...al between the inlet and outlet of the pump Interference between screws Reset the screw E clearance reset the timing gear Interference between screws and casing Reset the D clearance Blocked discharge nozzle or piping and increased back pressure Drain clean discharge nozzle and piping Overheat Excessive oil in FEC Check oil level and adjust the oil level if required High vacuum pump inlet temperat...

Page 19: ...Make sure the power supply is cut off SPECIAL TOOL LIST DESCRIPTION SPECIFICATION MATERIAL SDV 120 SDV 320 SDV 430 SDV 800 SDV 1500 SDV 2700 1 Bearing Pusher 3206 NJ206 Al bar 3208 NJ208 6207 Al bar 3308 6308 6207 NJ208 Al bar 3309 NJ309 3308 6308 Al bar 3216 2216 6314 Al bar 2 ea PTFE PTFE Aluminum 2 Mech Seal Pusher Special Aluminum 3 Lip Seal Puller Lip Seal Pusher Consult factory PTFE 4 Bearin...

Page 20: ...3 64 62 12 58 8 6 41 7 9 5 44 47 1 66 56 32 53 35 34 62 61 67 46 40 45 38 54 18 37 68 36 69 39 28 57 27 48 51 10 43 49 11 2 71 59 13 14 42 55 65 15 16 21 50 24 23 22 20 63 31 4 33 60 17 SDV 120 200 EXPLODED VIEW DRAWING NOTES ...

Page 21: ...1 TIMING GEAR A 1 32 TIMING GEAR B 1 33 POWER LOCK 2 34 LOCKNUT 1 35 LOCKWASHER 1 36 SEAL ADAPTER HOUSING 1 SDV 120 200 PARTS LIST ITEM NO DESCRIPTION QTY 37 MECHANICAL SEAL STATOR B 1 38 MECHANICAL SEAL ROTOR B 1 39 SEAL ADAPTER HOUSING COVER 1 40 BLIND PLATE A 1 41 BLIND PLATE B 1 42 BLIND PLATE C 1 43 BLIND PLATE D 1 44 KEY 1 45 SIGHT GLASS ASSEMBLY 2 46 BLIND PLATE GASKET A 1 47 BLIND PLATE GA...

Page 22: ...EW DRAWING NOTES 28 24 69 54 61 18 26 27 67 25 49 3 55 12 42 6 8 7 9 45 5 58 59 1 53 50 59 65 44 38 39 60 10 41 47 11 2 48 68 56 66 62 13 19 64 46 40 52 14 15 15 1 16 20 23 21 22 33 30 32 31 29 4 51 43 71 36 57 35 34 17 63 70 37 ...

Page 23: ...29 LOCKWASHER 2 30 GREASE COVER 2 31 TIMING GEAR A 1 32 TIMING GEAR B 1 33 POWER LOCK 2 34 LOCKNUT 1 35 LOCKWASHER 1 ITEM NO DESCRIPTION QTY 36 SEAL ADAPTER HOUSING 1 37 MECHANICAL SEAL STATOR B 1 38 MECHANICAL SEAL ROTOR B 1 39 SEAL ADAPTER HOUSING COVER 1 40 BLIND PLATE A 1 41 BLIND PLATE B 1 42 BLIND PLATE C 1 43 BLIND PLATE D 1 44 KEY 1 45 SIGHT GLASS ASSEMBLY 2 46 BLIND PLATE GASKET A 1 47 BL...

Page 24: ...EW DRAWING NOTES 28 69 54 24 25 27 26 18 67 61 3 49 55 12 8 9 7 5 59 50 6 39 42 1 59 53 45 58 44 38 65 41 10 47 64 11 2 46 40 52 48 56 13 66 68 62 19 14 51 33 15 1 22 23 20 16 30 29 21 60 31 32 43 4 57 63 17 34 37 35 36 70 15 71 ...

Page 25: ...R 2 29 TIMING GEAR A 1 30 TIMING GEAR B 1 31 POWER LOCK 2 32 LOCK NUT 1 33 LOCK WASHER 1 34 SEAL ADAPTER HOUSING 1 35 MECH SEAL STATOR 1 ITEM NO DESCRIPTION QTY 36 MECH SEAL ROTATOR 1 37 SEAL ADAP HOUSING COVER 1 38 BLIND PLATE A 1 39 BLIND PLATE B 1 40 BLIND PLATE C 1 41 BLIND PLATE D 1 42 KEY 1 43 SIGHT GLASS ASS Y 2 44 BLIND PLATE GASKET A 1 45 BLIND PLATE GASKET B 1 46 BLIND PLATE GASKET C 1 4...

Page 26: ... VIEW DRAWING NOTES 30 19 28 29 27 26 8 25 9 3 6 12 5 41 47 54 44 56 53 31 34 35 45 4 38 18 36 39 37 46 40 57 65 66 1 60 7 58 59 62 62 64 68 52 43 10 49 11 51 13 14 42 2 48 55 15 20 67 61 69 22 50 16 24 21 17 23 63 32 33 ...

Page 27: ...LOCK WASHER 2 30 GREASE COVER 2 31 TIMING GEAR A 1 32 TIMING GEAR B 1 33 POWER LOCK 2 34 LOCKNUT 1 35 LOCK WASHER 1 ITEM NO DESCRIPTION QTY 36 SEAL ADAPTER HOUSING 1 37 MECHANICAL SEAL STATOR B 1 38 MECHANICAL SEAL ROTOR B 1 39 SEAL ADAPTER HOUSING COVER 1 40 BLIND PLATE A 1 41 BLIND PLATE B 1 42 BLIND PLATE C 1 43 BLIND PLATE D 1 44 KEY 1 45 SIGHT GLASS ASSEMBLY 2 46 BLIND PLATE GASKET A 1 47 BLI...

Page 28: ...28 NEW SDV 320 EXPLODED VIEW DRAWING NOTES ...

Page 29: ... 2 29 TIMING GEAR A 1 30 TIMING GEAR B 1 31 POWER LOCK 2 32 LOCK NUT 1 33 LOCK WASHER 1 34 SEAL ADAPTER HOUSING 1 35 MECH SEAL STATOR B 1 36 MECH SEAL ROTATOR B 1 ITEM NO DESCRIPTION QTY 37 SEAL ADAPTER HOUSING COVER 1 38 BLIND PLATE A 1 39 BLIND PLATE B 1 40 BLIND PLATE C 1 41 BLIND PLATE D 1 42 KEY 1 43 SIGHT GLASS ASS Y 2 44 BLIND PLATE GASKET A 1 45 BLIND PLATE GASKET B 1 46 BLIND PLATE GASKET...

Page 30: ...VIEW DRAWING NOTES 27 43 10 49 64 58 11 51 13 14 22 50 42 2 48 55 15 16 24 21 17 23 20 68 70 62 54 31 33 52 32 34 35 45 4 38 18 36 39 37 66 67 60 6 41 47 44 57 53 46 40 1 59 63 63 5 30 19 28 29 26 8 25 3 12 65 69 61 56 7 9 ...

Page 31: ...HER 2 30 GREASE COVER 2 31 TIMING GEAR A 1 32 TIMING GEAR B 1 33 POWER LOCK 2 34 LOCKNUT 1 35 LOCK WASHER 1 ITEM NO DESCRIPTION QTY 36 SEAL ADAPTER HOUSING 1 37 MECHANICAL SEAL STATOR B 1 38 MECHANICAL SEAL ROTOR B 1 39 SEAL ADAPTER HOUSING COVER 1 40 BLIND PLATE A 1 41 BLIND PLATE B 1 42 BLIND PLATE C 1 43 BLIND PLATE D 1 44 KEY 1 45 SIGHT GLASS ASSEMBLY 2 46 BLIND PLATE GASKET A 1 47 BLIND PLATE...

Page 32: ...DRAWING NOTES 59 28 25 27 26 18 67 61 3 49 55 12 8 6 39 45 51 44 38 71 43 50 53 33 30 58 70 32 65 69 54 41 10 24 47 48 56 42 13 66 68 62 19 9 7 5 1 59 64 11 2 46 40 52 14 15 1 22 23 20 16 29 21 60 31 4 57 63 17 34 37 35 36 72 15 73 ...

Page 33: ...G GEAR A 1 30 TIMING GEAR B 1 31 POWER LOCK 2 32 LOCK NUT 1 33 LOCK WASHER 1 34 SEAL ADAPTER HOUSING 1 35 MECH SEAL STATOR 1 36 MECH SEAL ROTATOR 1 ITEM NO DESCRIPTION QTY 37 SEAL ADAP HOUSING COVER 1 38 BLIND PLATE A 1 39 BLIND PLATE B 1 40 BLIND PLATE C 1 41 BLIND PLATE D 1 42 KEY 1 43 SIGHT GLASS ASS Y 2 44 BLIND PLATE GASKET A 1 45 BLIND PLATE GASKET C 1 46 BLIND PLATE GASKET B 47 BLIND PLATE ...

Page 34: ...VIEW DRAWING NOTES 30 19 28 29 27 26 8 25 3 6 12 5 44 58 1 7 9 63 65 69 61 57 41 47 55 54 53 52 31 34 35 45 46 40 63 59 43 10 49 11 51 13 14 22 50 42 2 48 56 15 16 24 21 17 23 20 68 70 62 64 32 33 4 38 18 36 39 37 66 67 60 ...

Page 35: ...SHER 2 30 GREASE COVER 2 31 TIMING GEAR A 1 32 TIMING GEAR B 1 33 POWER LOCK 2 34 LOCKNUT 1 35 LOCK WASHER 1 ITEM NO DESCRIPTION QTY 36 SEAL ADAPTER HOUSING 1 37 MECHANICAL SEAL STATOR B 1 38 MECHANICAL SEAL ROTOR B 1 39 SEAL ADAPTER HOUSING COVER 1 40 BLIND PLATE A 1 41 BLIND PLATE B 1 42 BLIND PLATE C 1 43 BLIND PLATE D 1 44 KEY 1 45 SIGHT GLASS ASSEMBLY 2 46 BLIND PLATE GASKET A 1 47 BLIND PLAT...

Page 36: ...DRAWING NOTES 59 50 28 69 54 24 25 27 26 18 67 61 3 49 55 12 8 6 39 42 9 7 5 1 59 53 45 51 58 70 44 38 71 43 65 41 10 47 64 11 2 46 40 52 48 56 13 66 68 62 19 14 33 15 1 22 23 20 16 30 29 21 60 31 32 4 57 63 17 34 37 35 36 72 15 73 ...

Page 37: ...GEAR A 1 30 TIMING GEAR B 1 31 POWER LOCK 2 32 LOCK NUT 1 33 LOCK WASHER 1 34 SEAL ADAPTER HOUSING 1 35 MECH SEAL STATOR 1 36 MECH SEAL ROTATOR 1 ITEM NO DESCRIPTION QTY 37 SEAL ADAP HOUSING COVER 1 38 BLIND PLATE A 1 39 BLIND PLATE B 1 40 BLIND PLATE C 1 41 BLIND PLATE D 1 42 KEY 1 43 SIGHT GLASS ASS Y 2 44 BLIND PLATE GASKET A 1 45 BLIND PLATE GASKET B 1 46 BLIND PLATE GASKET C 47 BLIND PLATE GA...

Page 38: ...DV 1500 EXPLODED VIEW DRAWING NOTES 17 27 26 25 23 24 3 5 6 37 43 41 48 1 42 36 12 7 8 9 52 60 2 44 38 14 13 19 18 15 29 40 51 50 47 11 10 31 49 55 57 58 54 59 45 39 21 22 20 53 28 30 4 46 56 33 16 32 35 34 ...

Page 39: ...G 2 26 BEARING PUSHER 2 27 GREASE COVER 2 28 TIMING GEAR A 1 29 TIMING GEAR B 1 30 POWER LOCK 2 ITEM NO DESCRIPTION QTY 31 GEAR STOPPER 1 32 SEAL ADAPTER HOUSING 1 33 MECHANICAL SEAL STATOR 1 34 MECH SEAL ROTOR 1 35 DUST COVER 1 36 BLIND PLATE A 1 37 BLIND PLATE B 1 38 BLIND PLATE C 1 39 BLIND PLATE D 1 40 BLIND PLATE E 1 41 BLIND PLATE F 1 42 BLIND PLATE GASKET A 1 43 BLIND PLATE GASKET B 1 44 BL...

Page 40: ...SDV 2700 EXPLODED VIEW DRAWING NOTES 17 27 26 25 23 24 3 13 19 15 5 6 37 42 40 46 49 48 45 1 41 36 10 12 7 8 9 47 53 50 52 58 2 43 38 14 18 21 22 20 29 51 28 30 4 49 39 44 54 33 16 32 35 11 31 55 56 34 57 ...

Page 41: ... 6 25 LANTERN RING 2 26 BEARING PUSHER 2 27 GREASE COVER 2 28 TIMING GEAR A 1 29 TIMING GEAR B 1 ITEM NO DESCRIPTION QTY 30 POWER LOCK 1 31 GEAR STOPPER 1 32 SEAL ADAPTER HOUSING 1 33 MECHANICAL SEAL STATOR B 1 34 MECHANICAL SEAL ROTOR B 1 35 DUST COVER 1 36 BLIND PLATE A 1 37 BLIND PLATE B 1 38 BLIND PLATE C 1 39 BLIIND PLATE D 1 40 BLIND PLATE E 1 41 BLIND PLATE GASKET A 1 42 BLIND PLATE GASKET ...

Page 42: ...oid warranty Installation and transportation costs are not included and defective items must be held for Seller s inspection and returned to Seller s Ex works point upon request THERE ARE NO WARRANTIES EXPRESSED IMPLIED OR STATUTORY WHICH EXTEND BEYOND THE DESCRIPTION ON THE FACE HEREOF INCLUDING WITHOUT LIMITATION THE IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS OF PURPOSE After Buyer s subm...

Page 43: ...e Diameter Any other special accessories supplied or in use Motor Sheave Diameter Motor RPM HP NOTES IMPORTANT All KINNEY vacuum pumps manufactured by Tuthill Vacuum Blower Systems are date coded at time of shipment In order to assure you of the full benefits of the product warranty please complete tear out and return this product registration card Company _________________________________________...

Page 44: ...LED IN THE UNITED STATES ATTN CUSTOMER SERVICE VACUUM PRODUCTS TUTHILL VACUUM BLOWER SYSTEMS PO BOX 2877 SPRINGFIELD MO 65890 2150 POSTAGE WILL BE PAID BY ADDRESSEE BUSINESS REPLY MAIL FIRST CLASS MAIL PERMIT NO 2912 SPRINGFIELD MO ...

Reviews: