![Turbo Energy Lithium 48V 2.4 kWh Instruction Manual Download Page 11](http://html1.mh-extra.com/html/turbo-energy/lithium-48v-2-4-kwh/lithium-48v-2-4-kwh_instruction-manual_1181044011.webp)
11
Installation method 2: With simple bracket installation
4.4.3. Electrical installation
Before connecting the power cables, use multimeter to measure cable
continuity, short circuit, confirm positive and negative, and accurately mark the
cable labels.
Measuring methods
:
•
Power cable check: select the buzzer mode of multimeter and
detect both ends of the same color cable. If the buzzer calls, it
means the cable is in good condition.
•
Short circuit judgment: choose multimeter resistor file, probe the
same end of positive and negative pole, if the resistor shows infinity,
means that the cable is available.
•
After visual testing of power line is connection, the positive and
negative poles of the battery shall be connected respectively to
the positive and negative poles of the opposite terminal.
It is better to add a circuit breaker between the inverter and the battery system.
The selection of the circuit breaker requires:
1.
Place the Lithium Series 48V
2.4 kWh and brackets as
shown in the figure and insert
it into the brackets. Use 4
screws to fix the module on
the front bracket.
2.
Install
another
pair
of
brackets on the first one,
fixed by buckles between
them.
3.
Insert the second one
Lithium Series 48V 2.4 kWh
into the brackets and
repeat for more batteries.