Assembly
General information
Ducted particulate filters of Type KSFS are con-
nected directly to the duct via flanges using optional
spigots. The unit weight must be compensated by
on-site measures (suspensions or similar).
Fix the unit only to load-bearing structures.
Load suspension systems only with the weight
of the unit. Adjacent components and con-
necting ducts must be supported separately.
Do not unpack and insert/install the filter until
directly before commissioning.
NOTICE!
Possible malfunction due to a damaged
casing
If the casing has been damaged, unfiltered (con-
taminated) air may leak.
Do not drill any holes into the casing.
If there is a lengthy break between installation
and commissioning, cover all openings of the
casing (e.g. with plastic) to protect the interior
and avoid cumbersome cleaning procedures at
the time of commissioning.
Earthing connections KSFS-...-Ex
Fig. 2: Earthing connection
1
Earthing connection of filter casing
2
Earthing connection of filter chamber cover
3
Earthing connection of filter element (filter
chamber cover removed)
EXPLOSION HAZARD!
Connect the filter casing to the equipotential
bonding of the building via the earthing cable
(Fig. 2/1). When operating the explosion-proof
filter, all earthing cables must be installed, as
shown in Fig. 2.
Assembly
KSFS
∙
KSFS-...-Ex Ducted particulate filters
5