Rectangular duct
TVZ / TVA / TVM / TZ-/TA-Silenzio
Connection to ducting with air duct connections.
Make sure that the flange seal and screw connection M8x16 (to be provided by
others) are properly installed.
Position the ducting exactly. Do not pull the distances together via the air duct
connections.
TVJ / TVT
Connection to ducting with air duct connections.
Make sure that the flange seal and screw connection (to be provided by others)
are properly installed.
If necessary, insert additional duct clamps.
Position the ducting exactly. Do not pull the distances together via the air duct
connections.
Insulation
Fig. 29: Terminal unit with insulation, e.g. TVR-D
For VAV terminal units with acoustic cladding
(Fig. 29/1), lead the insulation of the room-end ducting
up to the acoustic cladding (Fig. 29/2) of the terminal
unit.
Retrofitting acoustic cladding
It is not possible to retrofit the factory acoustic clad-
ding to the VAV terminal unit.
Installation
Connecting the duct
VAV terminal units VARYCONTROL