Triple Solar assembly instruction PVT heat pump panels March 2020
10. Activating the system
Testing leak tightness, filling and system pressure
Attention:
Never pressurize the system with drinking water. You will never empty the system 100% and
the remaining drinking water will affect the glycol ratio in the system. The warranty provided by
Triple Solar (and Nibe) expires with immediate effect.
•
Always first pressurize the installation with air to detect leaks.
•
Check all gaskets and hydraulic connections for fluid tightness.
Tip:
Use a filling machine to obtain sufficient pressure and fluid velocity (flow). A filling machine can
also be used to remove all air from the system (see figure 7.10-a).