Enkapsis & EnerSure Platform Installation Guide Rev07.2
59
Startup and Use - EnerSure Bus & Bus2.0
Initial Startup
o
Make sure all electronic equipment is properly grounded before
connecting any live power.
o
Record the serial numbers of each Enkapsis PQM before installation.
o
Re-connect the power supply connector to the Enkapsis PQM. Note: If the
circuit breaker powering the power supply is turned on you will
immediately see the LED lights on the Enkapsis PQM. If the board is
currently being supplied power please turn the power off.
(Note: the CPU
takes approximately 10 seconds to reboot after the unit is powered off).
o
Before communicating with the Enkapsis PQM all CT’s should be
connected.
o
Apply power to the Enkapsis PQM.
o
Connect a Cat5 cable from the Enkapsis PQM to your computer.
o Applications of RS-485 use 9600, N, 8, 1.
o
The factory default network settings are:
o
IP address 10.10.10.4
o
Subnet Mask 255.0.0.0
o Gateway 10.10.10.1
Summary of Contents for ENKAPSIS
Page 1: ...Enkapsis EnerSure Platform Installation Guide ...
Page 19: ...Enkapsis EnerSure Platform Installation Guide Rev07 2 19 Common Current Transformers ...
Page 27: ...Enkapsis EnerSure Platform Installation Guide Rev07 2 27 iBCPM CT Strip Bracket Dimensions ...
Page 28: ...Enkapsis EnerSure Platform Installation Guide Rev07 2 28 CTStripAddressingDiagram ANSI IEC ...
Page 39: ...Enkapsis EnerSure Platform Installation Guide Rev07 2 39 Current Transformer Dimensions ...