Machine Maintenance Procedures
Disassembly Process
0
The disassembly process is divided into the following sections:
Main unit disassembly
LCD module disassembly
The flowcharts provided in the succeeding disassembly sections illustrate the entire
disassembly sequence. Observe the order of the sequence to avoid damage to any of the
hardware components. For example, when removing the heatsink, remove first the base
cover, battery, and fan module in that order.
Table 3-1. Main Screw List
Size
Quantity
Acer Part No.
SCREW M2.5*4.0-I(NI)(NYLOK)IRON
12
86.RYYN7.001
SCREW M2.5*2.5-I(BNI)(NYLOK)T=0.6
8
86.SHXN7.003
SCREW M3*0.5+3.5I
4
86.TDY07.003
M2.5*5.2
12
SCREW M2.0*3.0-I(BZN)(NYLOK)IRON
14