Trane K01K12345 Installation, Operation And Maintenance Manual Download Page 15

Installation

CLCH-SVX08C-EN

15 

Installing Indoor Flue Stacks

Gas heat sections for indoor air handlers require a field-
engineered and field-installed flue stack. Local codes and 
practices vary throughout the country. The engineer 
should size the flue based on MBh output, horizontal and 
vertical run lengths, type of flue material, NFPA 54 Fuel Gas 
Code, and local codes. The flue should be designed for 800 
degrees F (430 degrees C). If horizontal runs over 20 feet or 
other static-increasing transitions are necessary, a flue 
booster fan will be required.

Install according to local codes. See connection sizes in 

Table 5

.

Installing Rain Hood/Combustion Air Inlet

Rain hoods are only required on an outdoor unit with an 
internal vestibule. Depending on unit size, the combustion 
air opening will be in the access door or in the side panel. 
A unit with an external vestibule has the combustion air 
opening in the floor of the vestibule and does not require 
a rain hood, unless excessive snowdrifts are expected. 

Rain hoods for the combustion air opening ship loose and 
must be installed at the job site. The assembly consists of 
the hood, butyl tape and number 10 screws. 

Install butyl tape between the hood and the side panel 
or door panel (see 

Figure 7

).

Locate the bottom edge of the hood 2 3/8 inches below 
the bottom edge of the inlet air opening and center the 

hood left-to-right over the inlet air opening (see 

Figure 8

).

Install the hood to the unit with number 10 screws.

Installing Flue Stack for Hurricane 
Applications

Table 5.

Flue connection sizes for gas heat sections

Gas Output (MBh)

Flue Size (inches)

200, 320, 360, 560

8 × 8

 300

9 × 9

700, 860, 1000

12 × 12

1250, 1500, 1750

10 × 10

2000, 2400

14 x 14

Figure 7. Installation of rain hood for combustion air 

opening

Hood

Butyl tape

Figure 8. Center inlet air opening

Figure 9.

Flue stack installation for hurricane 
applications

Hinge

side

2 3/8 in.

Center hood left-to-right
over opening

Combustion
air opening

Rain hood

Access door

Airflow

Attach the gas heat flue duct 
to the L angles on both sides

Gas heat flue

See note

L bracket

Right side view

Note: 
When installing flue, leave enough clearance to avoid roof’s edge  and anything above the roof.

#10 x 3/4-in. self-drilling
sheet metal screws

Summary of Contents for K01K12345

Page 1: ...training Improperly installed adjusted or altered equipment by an unqualified person could result in death or serious injury When working on the equipment observe all precautions in the literature and...

Page 2: ...n which if not avoided could result in minor or moderate injury It could also be used to alert against unsafe practices NOTICE Indicates a situation that could result in equipment or property damage o...

Page 3: ...ion sizes for gas heat sections figure in Installation chapter Updated Duct Connection section in Installation chapter Added Gas heat internal piping penetration location and Gas heat external piping...

Page 4: ...stalling Outdoor Flue Stacks 14 Installing Indoor Flue Stacks 15 Installing Rain Hood Combustion Air Inlet 15 Installing Flue Stack for Hurricane Applica tions 15 Duct Connections 16 Combustion Air Du...

Page 5: ...handler section includes a nameplate label see Figure 1 which identifies the type of section customer tagging information the unit serial number the unit order number the build section position for in...

Page 6: ..._________________________________________ Altitude Above Sea Level___________________________________________________________________ Calorific Value___________________________________________________...

Page 7: ...gure 2 The external vestibule if required ships attached to the gas heat section Some heaters have gas train components in an internal vestibule see Figure 3 Refer to Table 2 for vestibule locations F...

Page 8: ...25 560 Ext 50 1750 Ext 120 1000 Int 25 700 Ext 50 2000 Ext 120 1250 Int 25 860 Ext 57 560 Int 120 1500 Int 25 1000 Ext 57 700 Int 120 1750 Int 30 320 360 Int 57 860 Int 120 2000 Int 30 560 Int 57 100...

Page 9: ...removed before assembly to the air handler Instruction Manuals Individual instruction manuals for all of the gas train components such as flame control relay valves pressure switches and actuators sh...

Page 10: ...or units that will be installed indoors However when outdoor storage is necessary several things must be done to prevent damage Note Keep the equipment on the original wooden blocks skid for protectio...

Page 11: ...ltage panel 61 61 61 61 61 61 61 61 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 D internal starter or VFD 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 E fan 48 48...

Page 12: ...75 85 50 92 50 107 50 119 75 119 75 Width 93 50 100 00 112 50 125 50 125 50 140 50 140 50 154 50 182 00 Height for outdoor unit includes base drip lip b 69 25 75 00 75 00 84 38 94 13 97 63 112 63 124...

Page 13: ...o the gas heat system if thesupply fan isshut off The gas heat system must not operate without the supply fan providing airflow All wiring must comply with applicable local and National Electric Code...

Page 14: ...ove the flue from inside the unit once the unit is assembled Installation High Altitude Installations Adjustment of gas train linkages is not normally required However for high altitude installations...

Page 15: ...r the combustion air opening ship loose and must be installed at the job site The assembly consists of the hood butyl tape and number 10 screws Install butyl tape between the hood and the side panel o...

Page 16: ...additional static pressure of the inlet air duct may change the fuel air ratio slightly necessitating system adjustment Separated combustion can be a desirable option but will require more field insta...

Page 17: ...on and Deadly Gases Never solder braze or weld on refrigerant lines or any unit components that are above atmospheric pressure or where refrigerant may be present Always remove refrigerant by followin...

Page 18: ...he same side as the gas train located inside the piping vestibule Since the drain line is equipped with a shut off valve a condensate p trap is not required but may be installed for convenience to avo...

Page 19: ...ield wiring poses FIRE and ELECTROCUTION hazards To avoid these hazards you MUST follow requirements for field wiring installation and grounding as described in NEC and your local state electrical cod...

Page 20: ...power the transformer TRANS1 Low Voltage Wiring The gas heat control system requires a binary signal for on off control Provide an interlock in the start stop signal circuit with the air handler supp...

Page 21: ...Wiring CLCH SVX08C EN 21 Figure 16 Natural gas 200 320 MBh 10 1 turndown...

Page 22: ...Wiring 22 CLCH SVX08C EN Figure 17 Natural gas 360 1000 MBh 3 1 and 10 1 turndown and propane 200 1000 MBh...

Page 23: ...Wiring CLCH SVX08C EN 23 Figure 18 Single phase natural gas and propane 1250 2000 MBh 3 1 and 10 1 turndown...

Page 24: ...Wiring 24 CLCH SVX08C EN Figure 19 3 Phase propane and natural gas 1250 2000 MBh 3 1 and 10 1 turndown with power exhaust...

Page 25: ...Wiring CLCH SVX08C EN 25 Figure 20 Natural gas and propane1250 2400 MBh 20 1 turndown...

Page 26: ...w g Attach another manometer to the burner manifold if optional gauge or sensor is not selected to check the burner manifold pressure when the unit is operational Typical pressure should be between 2...

Page 27: ...er assembly The following safety limit contracts should be closed HLl1 high temperature limit Al1 airflow interlock air handling fan should either be running or started 60 seconds after call for heat...

Page 28: ...ignition transformer and automatic gas valves will energize With the manual gas cocks closed the burner should go into a safety lockout condition The flame safeguard will have to be reset manually Tur...

Page 29: ...luminate The modulating gas valve actuator starts to open and the main light on the flame relay module should illuminate Note that it could take as long as 30 seconds for the actuator to fully open 6...

Page 30: ...d drain any accumulated condensate 3 Check all electrical terminals for tight connections 4 Open all manual gas valves and ensure that these valves operate freely 5 Check the air shutter and modulatin...

Page 31: ...densate from heat exchanger Weekly This task only needs to be done if the unit runs for extended hours at low fire Clean air inlet louver Monthly Use brush and vacuum cleaner Clean combustion air blow...

Page 32: ...gh Limit This switch trips due to a high temperature condition in the gas heat section Allow the air handler fan to run and cool heat exchanger The switch must be manually reset when the heat exchange...

Page 33: ...quate grounding and that it is properly located in the flame Also ensure that temperature at flame rod insulator is no greater than 500 F 260 C Perform Ignition Interference Test per component manufac...

Page 34: ......

Page 35: ......

Page 36: ...and protect food and perishables and increase industrial productivity and efficiency We are a global business committed to a world of sustainable progress and enduring results ingersollrand com Ingers...

Reviews: