6
88-A4AC3001-1G-EN
Section 3. Unit Preparation
3.1 Prepare The Unit For Installation
STEP 1
- Check for damage and report prompt-
ly to the carrier any damage found to the unit.
Section 4. Setting the Unit
4.1 Pad Installation
When installing the unit on a support pad, such
as a concrete slab, consider the following:
• The pad should be at least 1” larger than the
unit on all sides.
• The pad must be separate from any structure.
• The pad must be level.
• The pad should be high enough above grade
to allow for drainage.
• The pad location must comply with National,
State, and Local codes.
For other applications refer to application guide.