E6581810
Step6: Mount the EMC plate1 (Q) into both the conduit box (P) and the inverter with M6 screws. See
figure 14.
Caution
z
Be sure to install the EMC plate1 as figure 12 properly.
z
Do not operate the inverter without EMC plate1 properly in place.
Failure to follow this instruction can result in injury or equipment damage.
Step7: Install the EMC plate 2 (R) as shown in figure 15. This step is only for conduit box kit NEM1109Z.
R
Q
Figure 15
Figure 14
Step8: Install the conduit plate (S) with M4 screws. The knockouts provided are for control cables. Use
either a hole saw or a punch to cut entries for power cables. See figure 16.
Step9: Make all power and control connections to the inverter.
Step10: Install the conduit box cover (T) with M4 screws. See figure 17.
T
S
Figure 17
Figure 16
Step11: Replace the front cover (M) removed in step 2