3
Installing the Attachment
Mount
Parts needed for this procedure:
1
Stabilizer bracket
2
Carriage bolt (5/16 x 3/4 inch)
4
Locknut (5/16 inch)
2
Self-tapping screw (5/16 x 3/4 inch)
2
Bolt (5/16 x 1 inch)
1
Pivot frame
2
Hairpin cotter
2
Rod
2
Washer
1
Draw-bar decal
Procedure
1.
Install the stabilizer bracket to the engine guard
using 2 carriage bolts (5/16 x 3/4 inch) and 2
locknuts (5/16 inch) as shown in
.
g203564
Figure 6
1.
Stabilizer bracket
3.
Locknut (5/16 inch)
2.
Carriage bolt (5/16 x 3/4
inch)
2.
Install the pivot frame to the machine frame as
shown in
. Ensure that you push the
pivot frame up until it is tight against the bottom
of the engine guard. Loosely secure the pivot
frame to the machine frame using 2 bolts (5/16 x
1 inch) and 2 locknuts (5/16 inch).
g203563
Figure 7
1.
Machine frame
4.
Bolt (5/16 x 1 inch)
2.
Locknut (5/16 inch)
5.
Pivot frame
3.
Hole
3.
Secure the pivot frame to the bottom of the
machine frame using 2 self-tapping screws (5/16
x 3/4 inch) as shown in
g203566
Figure 8
1.
Self-tapping screw (5/16 x
3/4 inch)
2.
Pivot frame
4.
Tight the 2 bolts (5/16 x 1 inch) and 2 locknuts
(5/16 inch) from step
5.
Attach the draw bar decal 1.3 cm (1/2 inch) to
the left of the attachment mount (
8
Summary of Contents for 60in Bagger Kit